Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
08 Nov 2021 | Pipe laying progressing. | Alappuzha Project Dn PM | |
05 Nov 2021 | Pipe laying progressing. 594 m laid today. FHTC given 16. Total FHTC given 238 | Alappuzha Project Dn AE4 | |
31 Oct 2021 | Pipe laying progressing. 588 m laid today | Alappuzha Project Dn AE4 | |
27 Oct 2021 | Pipe laying progressing. 402 m laid today and 27 nos of FHTC provided | Alappuzha Project Dn AE4 | |
20 Oct 2021 | Work resumed today. Pipe laying progressing. 84 m laid today and 7 nos of FHTC provided | Alappuzha Project Dn AE4 | |
18 Oct 2021 | No work due to elevated water level | Alappuzha Project Dn AE4 | |
16 Oct 2021 | Pipe laying work started. 228 m of 90 mm PVC pipe laid and no of connections given is 7 | Alappuzha Project Dn AE4 | |
13 Oct 2021 | No work due to heavy rain. | Alappuzha Project Dn AE4 | |
08 Oct 2021 | Pipe supplied by Contractor | Alappuzha Project Dn AE4 | |
04 Oct 2021 | Pipe supply is pending due to non conducting test by CIPET | Alappuzha Project Dn AE4 |