08 Nov 2021 Pipe laying progressing. Alappuzha Project Dn PM
05 Nov 2021 Pipe laying progressing. 594 m laid today. FHTC given 16. Total FHTC given 238 Alappuzha Project Dn AE4
31 Oct 2021 Pipe laying progressing. 588 m laid today Alappuzha Project Dn AE4
27 Oct 2021 Pipe laying progressing. 402 m laid today and 27 nos of FHTC provided Alappuzha Project Dn AE4
20 Oct 2021 Work resumed today. Pipe laying progressing. 84 m laid today and 7 nos of FHTC provided Alappuzha Project Dn AE4
18 Oct 2021 No work due to elevated water level Alappuzha Project Dn AE4
16 Oct 2021 Pipe laying work started. 228 m of 90 mm PVC pipe laid and no of connections given is 7 Alappuzha Project Dn AE4
13 Oct 2021 No work due to heavy rain. Alappuzha Project Dn AE4
08 Oct 2021 Pipe supplied by Contractor Alappuzha Project Dn AE4
04 Oct 2021 Pipe supply is pending due to non conducting test by CIPET Alappuzha Project Dn AE4