Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
15 Jun 2022 | Laying of Pipes and providing FHTCs in progress. | Alappuzha Project Dn PM | |
05 Jan 2022 | Laying of pipeline and providing FHTC in progress | Alappuzha Project Dn PM | |
04 Jan 2022 | Work in progress, 3rd part bill submitted. | Alappuzha Project Dn PM | |
19 Dec 2021 | Work in progress, 2nd part bill submitted. | Alappuzha Project Dn AE4 | |
23 Nov 2021 | Work resumed. 330 m laid today. FHTC given 26. Total FHTC given 372 | Alappuzha Project Dn AE4 | |
19 Nov 2021 | No work due to high water table at site | Alappuzha Project Dn AE4 | |
16 Nov 2021 | No work due to heavy rain and site is flooded | Alappuzha Project Dn AE4 | |
13 Nov 2021 | No work due to heavy rain and site is flooded | Alappuzha Project Dn AE4 | |
11 Nov 2021 | Pipe laying progressing. 368 m laid today. FHTC given 20. Total FHTC given 348 | Alappuzha Project Dn AE4 | |
09 Nov 2021 | Pipe laying progressing. Total FHTC given 308 | Alappuzha Project Dn AE4 |