Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
15 Jun 2023 | Jal Jeevan Mission-Augmentation of ARWSS to Mannar Kurattissery-Pipe line extension and providing FHTC to Mannar and Chennithala Panchayaths-160mm pvc laying in Puthuvillapadi-Kuttamperoor road 250mm DI laying in Kallumoodu to Kottamuri road in chennithala panchayath | Alappuzha Project Dn PM | |
08 Jun 2023 | Mannar-Puthalapadi to kuttamperoor road 160 pvc laying - 15 nos Koikal jn kuttamperoor road 160 mm Pvc - 30 Ward- 14,Chember work ,90 mm pvc 80 mm valve,Chennithala Ward-7Concrete road,90 mm pvc Laying - 12nos Ward-8 Culvert crossing -80mm GI,90 mm pvc - 6 nos | Alappuzha Project Dn PM | |
01 Jun 2023 | Laid 160 mm PVC , 200mm DI pipe and house connections. | Alappuzha Project Dn PM | |
20 May 2023 | Laying 200 mm DI pipe kayamkulam - thiruvalla road,Laying 160mm PVC pipe @ mannar panchayath, House connections ward 7 Chennithala panchayath | Alappuzha Project Dn PM | |
15 May 2023 | Chennithala ,ward-10 House connection, FHTC | Alappuzha Project Dn PM | |
09 May 2023 | Kayamkulam to thiruvalla road laying 200 DI - 10 nos, 160 PVC - 10 nos, Chennithala panchayath Ward -11 Laying @ Mannar chennithala Panchayat 90 PVC - 30 nos Ward - 9 Interconnection 90 mm Ward -16 Connection HTC - 4nos | Alappuzha Project Dn PM | |
03 May 2023 | Chennithala Kayamkulam - thiruvalla road DI 200 mm culvert crossing , 160 MS culvert crossing ,Chennithala cherukol 75 to 90 mm PVC interconnection Measured and tagged 30 connection @ Mannar chennithala Panchayat | Alappuzha Project Dn PM | |
25 Apr 2023 | Jal Jeevan Mission-Augmentation of ARWSS to Mannar Kurattissery-Pipe line extension and providing FHTC to Mannar and Chennithala Panchayaths- 90mm Interconnection work and Gsb laying ward 10 | Alappuzha Project Dn PM | |
18 Apr 2023 | Jal Jeevan Mission-Augmentation of ARWSS to Mannar Kurattissery-Pipe line extension and providing FHTC to Mannar and Chennithala Panchayaths-Chennithala Ward 5 -Interconnection work(90 to 90) Mannar Ward 5- 6 fhtc ,Ward 6 -6FHTC ,Interconnection 90 mm Ward 18 Concreting 40m(Restoration) | Alappuzha Project Dn PM | |
12 Apr 2023 | Chennithala Ward 5 -Interconnection work(90 to 90) Mannar Ward 5- 6 fhtc ,Ward 6 -6FHTC ,Interconnection 90 mm Ward 18 Concreting 40m(Restoration) | Alappuzha Project Dn PM |