Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
13 Nov 2023 | Laid quantity: 90mm UPVC – 81569m 110mm UPVC – 8086m (completed)160mm UPVC – 48705m 300mm DI – 3491m (completed) 200mm DI – 4186m, 250mm DI – 1945m (completed) FHTCs provided: 8913 HTCs provided: 2378 | Alappuzha Project Dn PM | |
18 Oct 2023 | Pipe laying at cherukol,chennithala..160mm.PVC, out of 17920 FHTCs around 4070 FHTCs done. | Alappuzha Project Dn PM | |
26 Sep 2023 | out of 17920 FHTCs around 4070 FHTCs done. | Alappuzha Project Dn PM | |
14 Sep 2023 | House connection 14 nos, interconnection work Ward 4 chennithala | Alappuzha Project Dn PM | |
04 Sep 2023 | Chennithala panchayath. Thiruvalla - kayamkulam road. Pipe laying (160mm pvc) | Alappuzha Project Dn PM | |
14 Aug 2023 | Chennithala panchayath. Thiruvalla - kayamkulam road. Pipe laying (160mm pvc) | Alappuzha Project Dn AE 3 | |
19 Jul 2023 | Chennithala panchayath. Thiruvalla - kayamkulam road. Pipe laying (160mm pvc) | Alappuzha Project Dn PM | |
11 Jul 2023 | Laid 160m mm PVC -Kayamkulam ,Thiruvalla road ,Chamber work ward -11 @ Mannar Panchayath, House connection chennithala kallumoodu | Alappuzha Project Dn PM | |
03 Jul 2023 | Laid 160m mm PVC -Kayamkulam ,Thiruvalla road ,Chamber work ward -11@Mannar Panchayath, House connection chennithala kallumoodu . | Alappuzha Project Dn PM | |
22 Jun 2023 | Chennithala panchayath. Kallumood jn. Thiruvalla - kayamkulam road. Pipe laying (160mm pvc) | Alappuzha Project Dn PM |