Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
06 Apr 2024 | Laid quantity: 90mm UPVC – 81569m 110mm UPVC – 8086m (completed)160mm UPVC – 48705m 300mm DI – 3491m (completed) 200mm DI – 4186m, 250mm DI – 1945m (completed) Mannar FHTCs provided: 3414 HTCs provided: 2093, Chennithala FHTCs provided: 4164 HTCs provided: 1560 | Alappuzha Project Dn PM | |
20 Mar 2024 | Laid quantity: 90mm UPVC – 81569m 110mm UPVC – 8086m (completed)160mm UPVC – 48705m 300mm DI – 3491m (completed) 200mm DI – 4186m, 250mm DI – 1945m (completed) Mannar FHTCs provided: 3414 HTCs provided: 2093, Chennithala FHTCs provided: 4164 HTCs provided: 1560 | Alappuzha Project Dn PM | |
21 Feb 2024 | Laid quantity: 90mm UPVC – 81569m 110mm UPVC – 8086m (completed)160mm UPVC – 48705m 300mm DI – 3491m (completed) 200mm DI – 4186m, 250mm DI – 1945m (completed) Mannar FHTCs provided: 3414 HTCs provided: 2093, Chennithala FHTCs provided: 4164 HTCs provided: 1560 | Alappuzha Project Dn PM | |
12 Feb 2024 | Laid quantity: 90mm UPVC – 81569m 110mm UPVC – 8086m (completed)160mm UPVC – 48705m 300mm DI – 3491m (completed) 200mm DI – 4186m, 250mm DI – 1945m (completed) Mannar FHTCs provided: 3414 HTCs provided: 2093, Chennithala FHTCs provided: 4164 HTCs provided: 1560 | Alappuzha Project Dn PM | |
29 Jan 2024 | Laid quantity: 90mm UPVC – 81569m 110mm UPVC – 8086m (completed)160mm UPVC – 48705m 300mm DI – 3491m (completed) 200mm DI – 4186m, 250mm DI – 1945m (completed) Mannar FHTCs provided: 3414 HTCs provided: 2093, Chennithala FHTCs provided: 4164 HTCs provided: 1560 | Alappuzha Project Dn PM | |
11 Jan 2024 | Laid quantity: 90mm UPVC – 81569m 110mm UPVC – 8086m (completed)160mm UPVC – 48705m 300mm DI – 3491m (completed) 200mm DI – 4186m, 250mm DI – 1945m (completed) Mannar FHTCs provided: 3414 HTCs provided: 2093, Chennithala FHTCs provided: 4164 HTCs provided: 1560 | Alappuzha Project Dn PM | |
27 Dec 2023 | Laid quantity: 90mm UPVC – 81569m 110mm UPVC – 8086m (completed)160mm UPVC – 48705m 300mm DI – 3491m (completed) 200mm DI – 4186m, 250mm DI – 1945m (completed) FHTCs provided: 8913 HTCs provided: 2378 | Alappuzha Project Dn PM | |
20 Dec 2023 | Laid quantity: 90mm UPVC – 81569m 110mm UPVC – 8086m (completed)160mm UPVC – 48705m 300mm DI – 3491m (completed) 200mm DI – 4186m, 250mm DI – 1945m (completed) FHTCs provided: 8913 HTCs provided: 2378 | Alappuzha Project Dn PM | |
13 Dec 2023 | Laid quantity: 90mm UPVC – 81569m 110mm UPVC – 8086m (completed)160mm UPVC – 48705m 300mm DI – 3491m (completed) 200mm DI – 4186m, 250mm DI – 1945m (completed) FHTCs provided: 8913 HTCs provided: 2378 | Alappuzha Project Dn PM | |
06 Dec 2023 | Laid quantity: 90mm UPVC – 81569m 110mm UPVC – 8086m (completed)160mm UPVC – 48705m 300mm DI – 3491m (completed) 200mm DI – 4186m, 250mm DI – 1945m (completed) FHTCs provided: 8913 HTCs provided: 2378 | Alappuzha Project Dn PM |