| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 03 Jul 2023 | 89 km pipe laying work completed, laying work in progress,5342 FHTC completed. providing house connection is in progress | Valakom PH Sn AE | |
| 30 Jun 2023 | 89 km pipe laying work completed, laying work in progress,5342 FHTC completed. providing house connection is in progress | Valakom PH Sn AE | |
| 27 Jun 2023 | 89 km pipe laying work completed, laying work in progress,5342 FHTC completed. providing house connection is in progress | Valakom PH Sn AE | |
| 24 Jun 2023 | 89 km pipe laying work completed, laying work in progress,5342 FHTC completed. providing house connection is in progress | Valakom PH Sn AE | |
| 22 Jun 2023 | 89 km pipe laying work completed, laying work in progress,5342 FHTC completed. providing house connection is in progress | Valakom PH Sn AE | |
| 19 Jun 2023 | 82 km pipe laying work completed, laying work in progress,5107 FHTC completed. providing house connection is in progress | Valakom PH Sn AE | |
| 15 Jun 2023 | 82 km pipe laying work completed, laying work in progress,5107 FHTC completed. providing house connection is in progress | Valakom PH Sn AE | |
| 12 Jun 2023 | 82 km pipe laying work completed, laying work in progress,5107 FHTC completed. providing house connection is in progress | Valakom PH Sn AE | |
| 09 Jun 2023 | 82 km pipe laying work completed, laying work in progress,5107 FHTC completed. providing house connection is in progress | Valakom PH Sn AE | |
| 08 Jun 2023 | 82 km pipe laying work completed, laying work in progress,5107 FHTC completed. providing house connection is in progress | Valakom PH Sn AE |