| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 05 Jun 2023 | 82 km pipe laying work completed, laying work in progress,5107 FHTC completed. providing house connection is in progress | Valakom PH Sn AE | |
| 02 Jun 2023 | 82 km pipe laying work completed, laying work in progress,5107 FHTC completed. providing house connection is in progress | Valakom PH Sn AE | |
| 30 May 2023 | 82 km pipe laying work completed, laying work in progress,5107 FHTC completed. providing house connection is in progress | Valakom PH Sn AE | |
| 27 May 2023 | 82 km pipe laying work completed, laying work in progress,5107 FHTC completed. providing house connection is in progress | Valakom PH Sn AE | |
| 24 May 2023 | 82 km pipe laying work completed, laying work in progress,5107 FHTC completed. providing house connection is in progress | Valakom PH Sn AE | |
| 22 May 2023 | 82 km pipe laying work completed, laying work in progress,5107 FHTC completed. providing house connection is in progress | Valakom PH Sn AE | |
| 20 May 2023 | 82 km pipe laying work completed, laying work in progress,5107 FHTC completed. providing house connection is in progress | Valakom PH Sn AE | |
| 17 May 2023 | 82 km pipe laying work completed, laying work in progress,4960 FHTC completed. providing house connection is in progress | Valakom PH Sn AE | |
| 15 May 2023 | 82 km pipe laying work completed, laying work in progress,4960 FHTC completed. providing house connection is in progress | Valakom PH Sn AE | |
| 11 May 2023 | 82 km pipe laying work completed, laying work in progress,4960 FHTC completed. providing house connection is in progress | Valakom PH Sn AE |