| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 19 Oct 2023 | 89 km pipe laying work completed, laying work in progress,5991 FHTC completed. providing house connection is in progress | Valakom PH Sn AE | |
| 16 Oct 2023 | 89 km pipe laying work completed, laying work in progress,5991 FHTC completed. providing house connection is in progress | Valakom PH Sn AE | |
| 13 Oct 2023 | 89 km pipe laying work completed, laying work in progress,5991 FHTC completed. providing house connection is in progress | Valakom PH Sn AE | |
| 12 Oct 2023 | 89 km pipe laying work completed, laying work in progress,5991 FHTC completed. providing house connection is in progress | Valakom PH Sn AE | |
| 09 Oct 2023 | 89 km pipe laying work completed, laying work in progress,5991 FHTC completed. providing house connection is in progress | Valakom PH Sn AE | |
| 06 Oct 2023 | 89 km pipe laying work completed, laying work in progress,5991 FHTC completed. providing house connection is in progress | Valakom PH Sn AE | |
| 03 Oct 2023 | 89 km pipe laying work completed, laying work in progress,5991 FHTC completed. providing house connection is in progress | Valakom PH Sn AE | |
| 30 Sep 2023 | 89 km pipe laying work completed, laying work in progress,5991 FHTC completed. providing house connection is in progress | Valakom PH Sn AE | |
| 27 Sep 2023 | 89 km pipe laying work completed, laying work in progress,5991 FHTC completed. providing house connection is in progress | Valakom PH Sn AE | |
| 23 Sep 2023 | 89 km pipe laying work completed, laying work in progress,5991 FHTC completed. providing house connection is in progress | Valakom PH Sn AE |