Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
21 Sep 2023 89 km pipe laying work completed, laying work in progress,5991 FHTC completed. providing house connection is in progress Valakom PH Sn AE
19 Sep 2023 89 km pipe laying work completed, laying work in progress,5991 FHTC completed. providing house connection is in progress Valakom PH Sn AE
16 Sep 2023 89 km pipe laying work completed, laying work in progress,5919 FHTC completed. providing house connection is in progress Valakom PH Sn AE
15 Sep 2023 89 km pipe laying work completed, laying work in progress,5919 FHTC completed. providing house connection is in progress Valakom PH Sn AE
12 Sep 2023 89 km pipe laying work completed, laying work in progress,5919 FHTC completed. providing house connection is in progress Valakom PH Sn AE
08 Sep 2023 89 km pipe laying work completed, laying work in progress,5919 FHTC completed. providing house connection is in progress Valakom PH Sn AE
07 Sep 2023 89 km pipe laying work completed, laying work in progress,5919 FHTC completed. providing house connection is in progress Valakom PH Sn AE
04 Sep 2023 89 km pipe laying work completed, laying work in progress,5919 FHTC completed. providing house connection is in progress Valakom PH Sn AE
01 Sep 2023 89 km pipe laying work completed, laying work in progress,5919 FHTC completed. providing house connection is in progress Valakom PH Sn AE
22 Aug 2023 89 km pipe laying work completed, laying work in progress,5919 FHTC completed. providing house connection is in progress Valakom PH Sn AE