| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 21 Jun 2025 | Laying quantities as per schedule has been completed and remaining FHTCs work due to lack of work front issue in this work has been arranged JJM phase II work which is under LOA stage | Valakom PH Sn AE | |
| 06 Jun 2025 | 89km pipe Laying work and 6334 FHTC completed. providing FHTC in ward of additional pipe laying work | Valakom PH Sn AE | |
| 16 Apr 2025 | 89km pipe Laying work and 6334 FHTC completed. providing FHTC in ward of additional pipe laying work | Valakom PH Sn AE | |
| 28 Feb 2025 | 89km pipe Laying work and 6334 FHTC completed. providing FHTC in ward of additional pipe laying work | Valakom PH Sn AE | |
| 10 Feb 2025 | 89km pipe Laying work and 6334 FHTC completed. providing FHTC in ward of additional pipe laying work | Valakom PH Sn AE | |
| 28 Jan 2025 | 89km pipe Laying work and 6334 FHTC completed. providing FHTC in ward of additional pipe laying work | Valakom PH Sn AE | |
| 20 Jan 2025 | 89km pipe Laying work and 6334 FHTC completed. providing FHTC in ward of additional pipe laying work | Valakom PH Sn AE | |
| 04 Jan 2025 | 89km pipe Laying work and 6334 FHTC completed. providing FHTC in ward of additional pipe laying work | Valakom PH Sn AE | |
| 31 Dec 2024 | 89km pipe Laying work and 6334 FHTC completed. providing FHTC in ward of additional pipe laying work | Valakom PH Sn AE | |
| 17 Dec 2024 | 89km pipe Laying work and 6334 FHTC completed. providing FHTC in ward of additional pipe laying work | Valakom PH Sn AE |