| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 10 Feb 2023 | 4230 FHTC completed. work in progress | Valakom PH Sn AE | |
| 07 Feb 2023 | 4230 FHTC completed. work in progress | Valakom PH Sn AE | |
| 06 Feb 2023 | 4230 FHTC completed. work in progress | Valakom PH Sn AE | |
| 03 Feb 2023 | 4230 FHTC completed. work in progress | Valakom PH Sn AE | |
| 31 Jan 2023 | 4230 FHTC completed. work in progress | Valakom PH Sn AE | |
| 28 Jan 2023 | 4230 FHTC completed. work in progress | Valakom PH Sn AE | |
| 27 Jan 2023 | 4230 FHTC completed. work in progress | Valakom PH Sn AE | |
| 24 Jan 2023 | 4230 FHTC completed. work in progress | Valakom PH Sn AE | |
| 19 Jan 2023 | 4230 FHTC completed. work in progress | Valakom PH Sn AE | |
| 16 Jan 2023 | 4183 FHTC completed. work in progress | Valakom PH Sn AE |