Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
02 Feb 2021 | Package I- 91% Work Completed, Package II- 91% Work Completed, Package III- 99% Work Completed, Package IV- Work started .Soil Investigation completed , Structural Design of 15 LL OHSR is submitted to WASCON for approval. | Mattannur Project Sn 2 AE | |
25 Jan 2021 | Package I- 90% Work Completed, Package II- 91% Work Completed, Package III- 99% Work Completed, Package IV- Work started .Soil Investigation completed ,Structural Design of 15 LL OHSR is submitted to WASCON for approval. | Mattannur Project Sn 2 AE | |
30 Dec 2020 | Package I- 90% Completed, Package II-91% C ompleted, Packge III-99% Completed, Package IV- Work started | Mattannur Project Sn 2 AE | |
29 Nov 2020 | Package I -89% Completed Package II -90% Completed Package III -99 % Completed Package IV - Agreement executed on 20/11/2020 | Mattannur Project Sn 2 AE | |
27 Nov 2020 | Package I - 88% Completed. Package II - 89% Completed. Package III - 99% Completed. Package IV - Agreement executed on 20/11/2020 | Mattannur Project Sn 2 AE | |
06 Nov 2020 | Package I - 88% Completed. Package II - 89% Completed. Package III - 99% Completed. Package IV - Work order issued | Mattannur Project Sn 2 AE | |
12 Oct 2020 | Package I - 87% Completed. Package II - 89% Completed. Package III - 99% Completed. Package IV - Tendered | Mattannur Project Sn 2 AE | |
19 Aug 2020 | Package I - 86% Completed. Package II - 88% Completed. Package III - 99% Completed. Package IV - Tendered | Mattannur Project Sn 2 AE |