Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
11 Oct 2023 4 packages completed. Mattannur Project Sn 2 AE
29 Mar 2023 4 Packages 100% completed Mattannur Project Sn 2 AE
23 Jan 2023 Package I,II,III completed and commissioned on 13/8/2021.Package IV - 99% completed, Road reformation work is nearing completion. Mattannur Project Sn 2 AE
31 Jul 2022 Package I,II and III completed and commissioned on 13/08/2021.4 MLD water supplying to Mattannur Municipality and Keezhallur Panchayath by interconnection with existing tank at Kotheri .Package IV- 90 % work completed .OHSR plastering work , Road reformation work and compound wall construction works remaining. Mattannur Project Sn 2 AE
03 Jun 2022 Package I,II & III - Completed and commissioned on 13/08/2021, 4 MLD water supplying to Mattannur Municipality and Keezhallur Panchayath by interconnection with existing tank at Kotheri. Package IV- 80% work completed. Mattannur Project Sn 2 AE
02 Jun 2022 Package I,II & III - Completed and commissioned on 13/08/2021, 4 MLD water supplying to Mattannur Municipality and Keezhallur Panchayath by interconnection with existing tank at Kotheri. Package IV- 77 % work completed. Mattannur Project Sn 2 AE
18 Apr 2022 Package I,II & III - Completed and commissioned on 13/08/2021, 4 MLD water supplying to Mattannur Municipality and Keezhallur Panchayath by interconnection with existing tank at Kotheri. Package IV- 70 % work completed. Mattannur Project Sn 2 AE
16 Mar 2022 Package I,II &III-Completed and commissioned on 13/08/2021, 4 MLD water supplying to Mattannur Municipality and Keezhallur Panchayath by interconnection with existing tank at Kotheri. Package IV-15 LL OHSR-Structure completed, Plastering is in progress. Pumping main 200 mm DI K9 2230 m pipe supplied ,2040 m pipe laid Gravity main 450 mm DI K9 5709 m pipe supplied and 5503m laid, 400 mm DI K9 6864 m supplied and 6300m laid 200 mm DI gravity branch main 725 m pipe supplied. Interconnection 500 mm dia 424 m laid .Pipe laying is in progress. 3 LL GLSR at Manjakkunnu - Structure Completed Mattannur Project Sn 2 AE
04 Mar 2022 Package I,II &III-Completed and commissioned on 13/08/2021, 4 MLD water supplying to Mattannur Municipality and Keezhallur Panchayath by interconnection with existing tank at Kotheri. Package IV-15 LL OHSR-Structure completed, Plastering is in progress. Pumping main 200 mm DI K9 2040 m pipe laid Gravity main 450 mm DI K9 5709 m pipe supplied and 5503m laid, 400 mm DI K9 6864 m supplied and 5800m laid 200 mm DI gravity branch main 725 m pipe supplied. Interconnection 500 mm dia 424 m laid .Pipe laying is in progress. 3 LL GLSR - Side wall 3 rd lift completed. Mattannur Project Sn 2 AE
01 Feb 2022 Package I,II &III-Completed and commissioned on 13/08/2021, 4 MLD water supplying to Mattannur Municipality and Keezhallur Panchayath by interconnection with existing tank at Kotheri. Package IV-15 LL OHSR-Roof slab completed , 15LL OHSR - roof slab RCC completed. Plastering work is in progress. Pumping main 200 mm DI K9 2040 m pipe laid Gravity main 450 mm DI K9 5709 m pipe supplied and 5503m laid, 400 mm DI K9 6864 m supplied and 3500m laid 200 mm DI gravity branch main 725 m pipe supplied. Interconnection 500 mm dia 424 m laid .Pipe laying is in progress. 3 LL GLSR - PCC completed. Mattannur Project Sn 2 AE