Status Date |
Overall Project Status |
Project Officer |
Contact |
11 Oct 2023 |
4 packages completed. |
Mattannur Project Sn 2 AE |
|
29 Mar 2023 |
4 Packages 100% completed |
Mattannur Project Sn 2 AE |
|
23 Jan 2023 |
Package I,II,III completed and commissioned on 13/8/2021.Package IV - 99% completed, Road reformation work is nearing completion. |
Mattannur Project Sn 2 AE |
|
31 Jul 2022 |
Package I,II and III completed and commissioned on 13/08/2021.4 MLD water supplying to Mattannur Municipality and Keezhallur Panchayath by interconnection with existing tank at Kotheri .Package IV- 90 % work completed .OHSR plastering work , Road reformation work and compound wall construction works remaining. |
Mattannur Project Sn 2 AE |
|
03 Jun 2022 |
Package I,II & III - Completed and commissioned on 13/08/2021, 4 MLD water supplying to Mattannur Municipality and Keezhallur Panchayath by interconnection with existing tank at Kotheri. Package IV- 80% work completed. |
Mattannur Project Sn 2 AE |
|
02 Jun 2022 |
Package I,II & III - Completed and commissioned on 13/08/2021, 4 MLD water supplying to Mattannur Municipality and Keezhallur Panchayath by interconnection with existing tank at Kotheri. Package IV- 77 % work completed. |
Mattannur Project Sn 2 AE |
|
18 Apr 2022 |
Package I,II & III - Completed and commissioned on 13/08/2021, 4 MLD water supplying to Mattannur Municipality and Keezhallur Panchayath by interconnection with existing tank at Kotheri. Package IV- 70 % work completed. |
Mattannur Project Sn 2 AE |
|
16 Mar 2022 |
Package I,II &III-Completed and commissioned on 13/08/2021, 4 MLD water supplying to Mattannur Municipality and Keezhallur Panchayath by interconnection with existing tank at Kotheri. Package IV-15 LL OHSR-Structure completed, Plastering is in progress. Pumping main 200 mm DI K9 2230 m pipe supplied ,2040 m pipe laid Gravity main 450 mm DI K9 5709 m pipe supplied and 5503m laid, 400 mm DI K9 6864 m supplied and 6300m laid 200 mm DI gravity branch main 725 m pipe supplied. Interconnection 500 mm dia 424 m laid .Pipe laying is in progress. 3 LL GLSR at Manjakkunnu - Structure Completed |
Mattannur Project Sn 2 AE |
|
04 Mar 2022 |
Package I,II &III-Completed and commissioned on 13/08/2021, 4 MLD water supplying to Mattannur Municipality and Keezhallur Panchayath by interconnection with existing tank at Kotheri. Package IV-15 LL OHSR-Structure completed, Plastering is in progress. Pumping main 200 mm DI K9 2040 m pipe laid Gravity main 450 mm DI K9 5709 m pipe supplied and 5503m laid, 400 mm DI K9 6864 m supplied and 5800m laid 200 mm DI gravity branch main 725 m pipe supplied. Interconnection 500 mm dia 424 m laid .Pipe laying is in progress. 3 LL GLSR - Side wall 3 rd lift completed. |
Mattannur Project Sn 2 AE |
|
01 Feb 2022 |
Package I,II &III-Completed and commissioned on 13/08/2021, 4 MLD water supplying to Mattannur Municipality and Keezhallur Panchayath by interconnection with existing tank at Kotheri. Package IV-15 LL OHSR-Roof slab completed , 15LL OHSR - roof slab RCC completed. Plastering work is in progress. Pumping main 200 mm DI K9 2040 m pipe laid Gravity main 450 mm DI K9 5709 m pipe supplied and 5503m laid, 400 mm DI K9 6864 m supplied and 3500m laid 200 mm DI gravity branch main 725 m pipe supplied. Interconnection 500 mm dia 424 m laid .Pipe laying is in progress. 3 LL GLSR - PCC completed. |
Mattannur Project Sn 2 AE |
|