Overall Project Status

Status Date Overall Project Status Project Officer Contact
21 Apr 2021 Package 1- KSEB work going on. Electrical inspectorates inspection scheduled on 30/4/21 along with the supplierof Transformer, Kirloskar Mysore and supplier of pannel boards, Powertech,chennai. Package 2- Power line extension from KSEB to WTP going on. Package 3 completed, Final bill submitted. Package 4- Approved design of 15 LL OHSR received on 20/4/21 from WASCON. Mattannur Project Sn 2 AE
11 Apr 2021 PACKAGE I- Raw Water Pumping Main - 3280 m 750mm DI pipe laid. 750mm MS pipe laying completed. Intake well cum pump house - completed. Pipe carrying bridge completed. Transformer building - completed. Pannel board erection work completed. Pump set, motor etc erection completed. Retaining wall - completed. Watchman cabin completed. Side protection wall work is in progress. Drain work is in progress. Gate pillar and compound wall plastering completed.KSEB U G Cable laying completed. PACKAGE II-Clarifloculator 1&2 Completed. Clear Water Reservoirs 34 LL & 21 LL Completed. Aerator Completed. Chemical House Completed. Filter House finishing work is in progress. Mechanical work is in progress( Measuring Devises- Rate of Flow Controller and Loss of Head Guage installation completed). Filter media laying is in progress. Wash water tank completed. wash water lagoon completed. Drain completed. Watchman cabin completed. Compound wall completed. Electrical work (Panel board erection etc) completed. Plumbing & sanitary installation completed. Painting work is in progress. Pumpset and motor supplied . Hand rails for Clear water channel work completed. KSEB WORK-Powerline extension and transformer erection is in progress. PACKAGE III- Completed PACKAGE IV- Work started. Soil investigation for 15 LL OHSR at Iritty completed. Structural design of 15 LL OHSR submitted to WASCON for approval. Mattannur Project Sn 2 AE
30 Mar 2021 PACKAGE I- Raw Water Pumping Main - 3280 m 750mm DI pipe laid. 750mm MS pipe laying completed. Intake well cum pump house - completed. Pipe carrying bridge completed. Transformer building - completed. Pannel board erection work completed. Pump set, motor etc erection completed. Retaining wall - completed. Watchman cabin completed. Side protection wall work is in progress. Drain work is in progress. KSEB U G Cable laying completed. PACKAGE II-Clarifloculator 1&2 Completed. Clear Water Reservoirs 34 LL & 21 LL Completed. Aerator Completed. Chemical House Completed. Filter House finishing work is in progress. Mechanical work is in progress( Measuring Devises- Rate of Flow Controller and Loss of Head Guage installation completed). Filter media laying is in progress. Wash water tank completed. wash water lagoon completed. Drain completed. Watchman cabin plastering , electrification and plumbing completed. Compound wall completed. Electrical work (Panel board erection etc) is in progress. Plumbing & sanitary installation completed. Painting work is in progress. Pumpset and motor supplied . Hand rails for Clear water channel work is in progress. PACKAGE III- Completed PACKAGE IV- Work started. Soil investigation for 15 LL OHSR at Iritty completed. Structural design of 15 LL OHSR submitted to WASCON for approval. Mattannur Project Sn 2 AE
24 Mar 2021 PACKAGE I- Raw Water Pumping Main - 3280 m 750mm DI pipe laid. 750mm MS pipe laying completed. Intake well cum pump house - completed. Pipe carrying bridge completed. Transformer building - completed. Pannel board erection work completed. Pump set, motor etc erection completed. Retaining wall - completed. Watchman cabin completed. Side protection wall work is in progress. Drain work is in progress. KSEB U G Cable laying completed. PACKAGE II-Clarifloculator 1&2 Completed. Clear Water Reservoirs 34 LL & 21 LL Completed. Aerator Completed. Chemical House Completed. Filter House finishing work is in progress. Mechanical work is in progress. Filter media laying is in progress. Wash water tank completed. wash water lagoon completed. Drain completed. Watchman cabin plastering completed. Compound wall completed. Electrical work (Panel board erection etc) is in progress. Plumbing & sanitary installation completed. Painting work is in progress. Pumpset and motor supplied . Hand rails for Clear water channel work is in progress. PACKAGE III- Completed PACKAGE IV- Work started. Soil investigation for 15 LL OHSR at Iritty completed. Structural design of 15 LL OHSR submitted to WASCON for approval. Mattannur Project Sn 2 AE
18 Mar 2021 Package I & II- Finishing work is in progress. Package III-Completed , Package IV - started, Structural design of 15 LL OHSR submitted to WASCON for approval. Mattannur Project Sn 2 AE
09 Mar 2021 Package I & II- 95% Completed, Package III-Completed , Package IV - started, Structural design of 15 LL OHSR submitted to WASCON for approval. Mattannur Project Sn 2 AE
25 Feb 2021 Package I & II- 95% Completed,Package III-Completed , Package IV - started, Structural design of 15 LL OHSR submitted to WASCON for approval. Mattannur Project Sn 2 AE
19 Feb 2021 Package I & II- 91% Completed, Finishing work is in progress, Package III-Completed ,Package IV - started, Structural design of 15 LL OHSR submitted to WASCON for approval. Mattannur Project Sn 2 AE
12 Feb 2021 Package I- Finishing work is in progress ,91% Work Completed, Package II- Finishing work is in progress,91% Work Completed, Package III- 100% Work Completed, Package IV- Work started .Soil Investigation completed , Structural Design of 15 LL OHSR is submitted to WASCON for approval. Mattannur Project Sn 2 AE
09 Feb 2021 Package I- Finishing work is in progress ,91% Work Completed, Package II- Finishing work is in progress,91% Work Completed, Package III- 99% Work Completed, Package IV- Work started .Soil Investigation completed , Structural Design of 15 LL OHSR is submitted to WASCON for approval. Mattannur Project Sn 2 AE