Overall Project Status

Status Date Overall Project Status Project Officer Contact
07 Jul 2021 Package I-Fund received for HT service connection from HO on 06/07/2021, Package II - Fund received for LT service connection from HO on 06/07/2021 ,Package III- Completed , Final bill submitted, Package IV- OHSR plinth beam completed. 200 mm DI pumping main and 450mm DI gravity main pipe laying work started Mattannur Project Sn 2 AE
29 Jun 2021 Package I-Fund request ( CD ) for HT service connection for Rs40.75 lakhs submitted to HO on 25/06/2021, Package II - Fund request for LT service connection for Rs.1.13 lakhs submitted to HO on 25/06/2021 ,Package III- Completed , Final bill submitted, Package IV- OHSR plinth beam reinforcement work is in progress Mattannur Project Sn 2 AE
21 Jun 2021 Package I-Electrical Inspectorate inspection held on 30.04.2021.Based on defect report compliance report submitted. Inspectorate approval came on 24.05.2021.Application for HT service connection submitted on 01.06.2021.DCE (KSEB) inspected site on 15.06.2021. Package II- Completed except trial run and commissioning Package III- Completed , Final bill submitted Package IV- 15 LL OHSR Column up to plinth beam RCC completed Mattannur Project Sn 2 AE
12 Jun 2021 Package 1 - Completed except Trial run and commissioning, Package 2 - Completed except Trial run and commissioning ,Package 3-Completed ,Package 4- 15 LL OHSR Column PCC Completed. Column footing RCC completed Mattannur Project Sn 2 AE
10 Jun 2021 Package 1 - Completed except Trial run and commissioning, Package 2 - Completed except Trial run and commissioning ,Package 3-Completed ,Package 4- 15 LL OHSR Column PCC Completed. Column footing RCC ongoing Mattannur Project Sn 2 AE
31 May 2021 Package 1 - Completed except Trial run and commissioning, Package 2 - Completed except Trial run and commissioning ,Package 3-Completed ,Final bill submitted, Package 4- 15 LL OHSR Column PCC Completed. Mattannur Project Sn 2 AE
21 May 2021 Package 1- Electrical inspectorates inspection conducted . Package 2- Power line extension from KSEB to WTP completed. Package 3- completed, Final bill submitted. Package 4- Approved design of 15 LL OHSR received on 20/4/21 from WASCON. Earth work excavation started Mattannur Project Sn 2 AE
14 May 2021 Package 1- KSEB work going on. Electrical inspectorates inspection conducted with the supplier of Transformer, Kirloskar Mysore and supplier of pannel boards, Powertech,chennai. Package 2- Power line extension from KSEB to WTP completed. Package 3 completed, Final bill submitted. Package 4- Approved design of 15 LL OHSR received on 20/4/21 from WASCON. Earth work excavation started Mattannur Project Sn 2 AE
07 May 2021 Package 1- KSEB work going on. Electrical inspectorates inspection conducted with the supplier of Transformer, Kirloskar Mysore and supplier of pannel boards, Powertech,chennai. Package 2- Power line extension from KSEB to WTP going on. Package 3 completed, Final bill submitted. Package 4- Approved design of 15 LL OHSR received on 20/4/21 from WASCON. Earth work excavation started Mattannur Project Sn 2 AE
28 Apr 2021 Package 1- KSEB work going on. Electrical inspectorates inspection scheduled on 30/4/21 along with the supplier of Transformer, Kirloskar Mysore and supplier of pannel boards, Powertech,chennai. Package 2- Power line extension from KSEB to WTP going on. Package 3 completed, Final bill submitted. Package 4- Approved design of 15 LL OHSR received on 20/4/21 from WASCON. Mattannur Project Sn 2 AE