Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
12 Jan 2022 Package I,II and III- Completed and commissioned on 13/08/2021, 4 MLD water supplying to Mattannur Municipality and Keezhallur Panchayath by interconnection with existing tank at Kotheri .Package IV- 15LL OHSR -Floor slab RCC completed. Haunch RCC completed. Side wall RCC Ist lift completed. Side wall 2nd lift RCC Completed. Side wall 3 rd lift RCC completed. Roof slab RCC completed. Pumping main 200 mm DI K9 2040 m pipe laid Gravity main 450 mm DI K9 5709 m pipe supplied and 5503m laid, 400 mm DI K9 6864 m supplied and 2600 m laid 200 mm DI gravity branch main 725 m pipe supplied. Interconnection 500 mm dia 424 m laid .Pipe laying is in progress. 3 LL GLSR - Earth work excavation is in progress Mattannur Project Sn 2 AE
21 Dec 2021 Package I ,II,and III- Completed and commissioned on 13/08/2021 , 4 MLD water suppling to Mattannur Municipality and Keezhallur Panchayath by interconnection with existing tank at Kotheri.Package IV- 15LL OHSR -Floor slab RCC completed.Haunch RCC completed. Side wall RCC Ist lift completed. Side wall 2nd lift RCC Completed. Side wall 3 rd lift RCC completed. Roof slab shuttering work is in progress. Pumping main 200 mm DI K9 2230 supplied and 2040 m pipe laid. Gravity main 450 mm DI K9 5450 m pipe supplied and laid, 400 mm DI K9 2550 m pipe supplied and 670 m laid.Interconnection 500mm DI K9 450 m pipe supplied and 424m laid. 200 mm DI K9 pipe for gravity branch main - 725 m pipe supplied.Pipe laying is in progress Mattannur Project Sn 2 AE
20 Dec 2021 Package I- Trial run and commissioning completed, Package II- Trial run and commissioning completed, Package III- completed ,final bill received -Package IV- 15LL OHSR -Floor slab RCC completed.Haunch RCC completed. Side wall RCC Ist lift completed. Side wall 2nd lift RCC Completed. Side wall 3 rd lift RCC completed. Roof slab shuttering work is in progress. Pumping main 200 mm DI K9 2230 supplied and 2040 m pipe laid. Gravity main 450 mm DI K9 5450 m pipe supplied and laid, 400 mm DI K9 2550 m pipe supplied and 670 m laid.Interconnection 500mm DI K9 450 m pipe supplied and 424m laid. 200 mm DI K9 pipe for gravity branch main - 725 m pipe supplied.Pipe laying is in progress Mattannur Project Sn 2 AE
17 Dec 2021 Package I- Trial run and commissioning completed, Package II- Trial run and commissioning completed, Package III- completed ,final bill received -Package IV- 15LL OHSR -Floor slab RCC completed.Haunch RCC completed. Side wall RCC Ist lift completed. Side wall 2nd lift RCC Completed. Side wall 3 rd lift RCC completed. Pumping main 200 mm DI K9 2230 supplied and 2040 m pipe laid. Gravity main 450 mm DI K9 5450 m pipe supplied and laid, 400 mm DI K9 2550 m pipe supplied and 670 m laid. 450 m pipe supplied and 424m laid. 200 mm DI K9 pipe for gravity branch main - 725 m pipe supplied Mattannur Project Sn 2 AE
10 Dec 2021 Package I- Trial run and commissioning completed, Package II- Trial run and commissioning completed, Package III- completed ,final bill received -Package IV- 15 LL OHSR- Side wall 3rd lift RCC completed, pumping main , gravity main laying work is in progress Mattannur Project Sn 2 AE
01 Dec 2021 Package I- Trial run and commissioning completed,Package II- Trial run and commissioning completed, Package III- completed ,final bill received -Package IV- 15 LL OHSR- Side wall 2 nd lift RCC completed, pumping main , gravity main laying work is in progress Mattannur Project Sn 2 AE
03 Nov 2021 Package I- Trial run and commissioning completed,Package II- Trial run and commissioning completed, Package III- completed ,final bill received -Package IV- 15 LL OHSR- Base slab RCC completed, pumping main , gravity main laying work is in progress Mattannur Project Sn 2 AE
22 Sep 2021 Package I- Trial run and commissioning completed,Package II- Trial run and commissioning completed, Package III- completed ,final bill received -Package IV- 15 LL OHSR- Intermediate slab RCC completed, pumping main , gravity main laying work is in progress Mattannur Project Sn 2 AE
04 Sep 2021 Package I- completed,Package II- completed, Package III- completed ,final bill received -Package IV- 15 LL OHSR- Intermediate slab RCC completed, pumping main gravity main laying work is in progress Mattannur Project Sn 2 AE
26 Aug 2021 Package I- completed,Package II- completed, Package III- completed ,final bill received -Package IV- 15 LL OHSR- Intermediate slab shuttering and reinforcement work completed, pumping main gravity main laying work is in progress Mattannur Project Sn 2 AE