Overall Project Status

Status Date Overall Project Status Project Officer Contact
23 Apr 2024 1. Concreting of Filter house wall and beam 1st lift completed. Structural work of sump, clarifier, chlorine room are completed, erection of clarifier bridge in progress. 2. 942m of 400mm DI pumping main at west Kodur, 312.50 m of 250mm DI distribution line at Mundakode, 1040.50m of 200mm DI pumping main and 90mm rider at Mundakode, 1226m of 200mm DI Distribution line along with 1226m of 90mm rider at Vataparambu, 18236m of 90mm, 2450m of 110mm, 723m of 140mm, 2836m of 160mm and 728m of 180mm HDPE pipes laying in progress. Pipe laying work in progress. More pipes arriving. 350 HTC geotagged and going on. No ISA functioning in panchayath. Pipe testing almost completed. The Panchayath members and public raising objections to dig road for pipe line. 3. Side wall concreting 2nd lift completed for 16 LL tank at Kalanparamba. Pump house work nearing completion. The Panchayath authorities not peg marked location for & LL OHSR and hence, the work not started. Malappuram Sn AE 1
06 Nov 2023 WTP:- Concreting of central shaft of clarifier completed. Earthwork of filter bed started. Sklelton work of sump completed Distribution network:- DI pipes not yet arrived. The pump sets will arrive within 2 months. HTC started. The ward members not co-operate for pipe laying work .No ISA functioning in panchayath. Pipe laying in ward No.1 started. The masonry work nearing completion for the pump house. The plastering work progressing. The concreting of columns above third brace beam completed in 16 LL Tank. Work not started to 7 LL tank since the process of handing over the sufficient land by Panchayath not yet completed . Letter submitted to panchayath for speed up this process Malappuram Sn AE 1
26 Sep 2023 In WTP work, The centering work for 2nd lift of the sump wall above the haunch is completed. DI pipe for the scour and inlet of the clarifier is arrived. The centering work of the beams of Chlorinator room started. In distribution works, Hard laterite strata met in the trenches of pipelines in various places. DI pipes are to be arrived. The pump sets will arrive within 2 months.PWD AE insisted to give a new application for road-cutting permission in the ROW portal as per the recent circular by PWD. In Package 2, The lintel and sunshade are completed. The columns of OHSR reached up to 7.00 m. Since the process of handing over sufficient land (Required additional land of 100 sqm) for the 7.00 LL OHSR has not been started. Malappuram Sn AE 1
26 Sep 2023 In WTP work, The centering work for 2nd lift of the sump wall above the haunch is completed. DI pipe for scur &n inlet of the clarifier is arrived. Beam of Chlorinator room started. In distribution works, Hard laterite strata met in the trenches of pipelines in various places. DI pipes are to be arrived. The pump sets will arrive within 2 months. In Package 2, The lintel and sunshade are completed. The columns of OHSR reached up to 7.00 m. Since the process of handing over sufficient land (Required additional land of 100 sqm) for the 7.00 LL OHSR has not been started. Malappuram Sn AE 1
16 Sep 2023 In WTP work, The 1st lift of the sump wall above the haunch is completed. DI pipe for scur &n inlet of the clarifier have to be arrived. In distribution works, Hard laterite strata met in the trenches of pipelines in various places. DI pipes to be arrived. The pump sets will arrive within 2 months. In Package 2, The masonry works for the pump house reached up to the lintel level. The columns of OHSR reached up to 7.00 m. Malappuram Sn AE 1
11 Sep 2023 1.The concreting work of sump completed up to the Haunch level. ThePCC work for clarifier bottom is completed and reinforcement work progressing. The Plinth belt of Chlorine room is completed. 2.DI pipe has not arrived. PE pipe laying work progressing at Vadakkemanna. 3. The column above the floor slab of the well and the masonry work is progressing. For 16.00 LL OHSR, the columns above the 1st brace beams are progressing. 2nd part bill is under preparation. No ISA is functioning in Kodur Panchayath. Malappuram Sn AE 1
30 Aug 2023 The DI pipe not arrived yet and work for HDPE pipe is slow progress by insufficient response by Panchayath members. The concreting of the floor slab, and approach bridge of the well are completed. The columns above the well is in progress. The concreting of 1st overhead brace beams are progressing. Land handed over by the panchayath for constructing 7.00 OHSR at Vattapparambu is insufficient and Panchayath president being try to avail balance land needed. The floor slab of sump at Kalamparambu completed. Floor slab of Sump at WTP completed. No dept. vehicle in this section from March 2023 onward and supervising JJM works and mace works facing difficulties. No ISA working in Kodur Panchayath. Malappuram Sn AE 1
18 Aug 2023 In WTP work, PCC of Sump column footing completed. The Earthwork for clarifloculator is in progress. In Distribution work, the work at Vattapparambu started. The DI pipes have not arrived yet. The shuttering work and reinforcement works at NK padi is in good progress, The deck slab cum approach bridge would materialized soon. The centering work of the first over head brace of 16.00 LL is started. The land for OHSR at Vattapparmbu was obtained, but due to its topography and shape, land is insufficient to comfortably accommodate 7.00 LL. An additional 100 Sq.m asked to Panchayath and will obtained soon, the paperwork is in the pipeline at the Panchayath office. Malappuram Sn AE 1
08 Aug 2023 The sump and pump house, flocultor peg marked and foundation trenching started. The work is continuing at Vattapparambu. The soil condition in major portions is hard laterite; hence, digging has complications on narrow roads. The centering for the floor slab and approach bridge is progressing Malappuram Sn AE 1
29 Jul 2023 leveling for the sump at the back side on going. The work is interrupting by rain. The work started in the Urdu nagar and Vattapprambu areas. The DI pipes have not yet arrived. The concreting of the plinth beam will complete on 31-07-2023. Backfilling work inside plinth up to the bottom level had completed. Malappuram Sn AE 1