Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
19 Apr 2022 | Soil exploration completed. The firm not submitted the report, follow ups being done | Malappuram PH Dn EE | |
09 Apr 2022 | Trail boring completed. | Malappuram Sn AE 1 | |
06 Apr 2022 | Trail boring completed | Malappuram Sn AE 1 | |
31 Mar 2022 | Trail boring will conduct today | Malappuram Sn AE 1 | |
28 Mar 2022 | Trail boring scheduled to start today. Postponed due to national strike | Malappuram Sn AE 1 | |
23 Mar 2022 | Designing of WTP & Other components are in progress | Malappuram Sn AE 1 | |
22 Mar 2022 | Designing of WTP & Other components are in progress | Malappuram PH Dn EE | |
17 Mar 2022 | TS issued on 18.01.2022. Designing of WTP & Other components are in progress | Malappuram Sn AE 1 | |
15 Mar 2022 | TS issued on 18.01.2022. Designing of WTP & Other components are in progress. | Malappuram Sn AE 1 | |
08 Mar 2022 | TS issued on 18.01.2022. Designing of WTP & Other components are in progress. | Malappuram Sn AE 1 |