Status Date |
Overall Project Status |
Project Officer |
Contact |
03 May 2023 |
1- Package1 - 3% (HDPE pipe supply in progress. The laying work started at Peringottupulam. Supply order to DI Pipes has been gven, but not arrived.)
2- package 2 - 7% completed ( The sub floor of well concrete completed.The sub floor of well concrete completed.)
3 - Package 3- (Work tendered.) |
Malappuram PH Dn EE |
|
27 Apr 2023 |
HDPE pipe arriving.Laying work started at Peringottupulam.
Well steining work progressing, leading channel concrete completed. River side protection work progressing.
The registeration of dept Vehicle cancelled and with out conveyance facilities, the super vision of work not possible. |
Malappuram Sn AE 1 |
|
07 Apr 2023 |
HDPE pipe arriving.
Well steining work progressing, leading channel concrete completed.
The registeration of dept Vehicle cancelled and facing difficulties to supervise the works. |
Malappuram Sn AE 1 |
|
31 Mar 2023 |
Work arranged as three packages Package 1 -Distribution system Application sent for road cutting permissions,which is Processing at PWD office . Pipe ordered , HDPE pipes arriving. Package 2 - Well steining concrete progressing above 7.3m, work progressing Package 3 - WTP - work tendered from CE's office |
Malappuram Sn AE 1 |
|
22 Mar 2023 |
Work arranged as three packages Package 1 -Distribution system Application sent for road cutting permissions,which isProcessing at PWD office . Pipe ordered , but not arrived. Package 2 - Well steining concrete completed upto 7.3m, work progressing Package 3 - WTP - Resubmitted for TS, scrutiny at CE's office |
Malappuram PH Dn EE |
|
14 Feb 2023 |
Work arranged as three packages
Package 1 -Distribution system Application sent for road cutting permission three times, but PWD revert it. Pipe ordered. Package 2 - Well steining concrete completed upto 2.50m, work progressing Package 3 - WTP - Resubmitted for TS, scrutiny at CE's office |
Malappuram Sn AE 1 |
|
13 Feb 2023 |
Work splatted as three packages
Package 1 -Distribution system Application sent for road cutting permission three times, but PWD revert it. Pipe ordered.
Package 2 - Well steining concrete completed upto 2.50m, work progressing Package 3 - WTP - Resubmitted for TS, scrutiny at CE's office |
Malappuram Sn AE 1 |
|
10 Feb 2023 |
Package 1 -Application sent for road cutting permission three times, but PWD revert it Package 2 - Well steining concrete completed upto 2.50m , Package 3 - Resubmitted for TS, scrutiny at CE's office |
Malappuram Sn AE 1 |
|
19 Jan 2023 |
Package 1 - Order placed for pipe supply, Package 2 - The earth work for the well will start in 2 days , Package 3 - Resubmitted for TS |
Malappuram PH Dn EE |
|
29 Dec 2022 |
Pkg 1 & Pkg 2 - work awarded and agreement executed,
Pkg3- Estimate under scrutiny at CE's office |
Malappuram PH Dn EE |
|