Overall Project Status

Status Date Overall Project Status Project Officer Contact
03 May 2023 1- Package1 - 3% (HDPE pipe supply in progress. The laying work started at Peringottupulam. Supply order to DI Pipes has been gven, but not arrived.) 2- package 2 - 7% completed ( The sub floor of well concrete completed.The sub floor of well concrete completed.) 3 - Package 3- (Work tendered.) Malappuram PH Dn EE
27 Apr 2023 HDPE pipe arriving.Laying work started at Peringottupulam. Well steining work progressing, leading channel concrete completed. River side protection work progressing. The registeration of dept Vehicle cancelled and with out conveyance facilities, the super vision of work not possible. Malappuram Sn AE 1
07 Apr 2023 HDPE pipe arriving. Well steining work progressing, leading channel concrete completed. The registeration of dept Vehicle cancelled and facing difficulties to supervise the works. Malappuram Sn AE 1
31 Mar 2023 Work arranged as three packages Package 1 -Distribution system Application sent for road cutting permissions,which is Processing at PWD office . Pipe ordered , HDPE pipes arriving. Package 2 - Well steining concrete progressing above 7.3m, work progressing Package 3 - WTP - work tendered from CE's office Malappuram Sn AE 1
22 Mar 2023 Work arranged as three packages Package 1 -Distribution system Application sent for road cutting permissions,which isProcessing at PWD office . Pipe ordered , but not arrived. Package 2 - Well steining concrete completed upto 7.3m, work progressing Package 3 - WTP - Resubmitted for TS, scrutiny at CE's office Malappuram PH Dn EE
14 Feb 2023 Work arranged as three packages Package 1 -Distribution system Application sent for road cutting permission three times, but PWD revert it. Pipe ordered. Package 2 - Well steining concrete completed upto 2.50m, work progressing Package 3 - WTP - Resubmitted for TS, scrutiny at CE's office Malappuram Sn AE 1
13 Feb 2023 Work splatted as three packages Package 1 -Distribution system Application sent for road cutting permission three times, but PWD revert it. Pipe ordered. Package 2 - Well steining concrete completed upto 2.50m, work progressing Package 3 - WTP - Resubmitted for TS, scrutiny at CE's office Malappuram Sn AE 1
10 Feb 2023 Package 1 -Application sent for road cutting permission three times, but PWD revert it Package 2 - Well steining concrete completed upto 2.50m , Package 3 - Resubmitted for TS, scrutiny at CE's office Malappuram Sn AE 1
19 Jan 2023 Package 1 - Order placed for pipe supply, Package 2 - The earth work for the well will start in 2 days , Package 3 - Resubmitted for TS Malappuram PH Dn EE
29 Dec 2022 Pkg 1 & Pkg 2 - work awarded and agreement executed, Pkg3- Estimate under scrutiny at CE's office Malappuram PH Dn EE