24 Jul 2023 The site leveling of the sump of WTP was started, but rain hinter the works. The full area required for the Vattapparambu tank has not been handed over by the Panchayath. The concreting of the plinth brace of a portion of Kalamparambu tank was completed. The approach bridge is in progress. Heavy rain started and hence, excavation for distribution not possible since the public raise objections. Malappuram Sn AE 1
17 Jul 2023 WTP Design under verification. Intake well work reached near the subfloor level and the subfloor level slab of the approach bridge completed. The Kalalanprambu tank work reached upto the plinth level. Distribution network ongoing. Malappuram Sn AE 1
30 Jun 2023 LOA has been approved and design work is ongoing. The letter submitted to KSEB for temporary power connection Site levelling of Vattapparambu tank completd. The footing concrete of Kalanparambu tank progressing. The side protection work of intake structure also in progress. As the rain started, the public raises objections for cutting the road. In some areas, the strata is very hard laterite rock. The Panchayath members not co-operate with work and no ISA functioning in Panchayath Malappuram Sn AE 1
26 Jun 2023 Package 1 - DI pipes have not arrived. As the rain started, the public raises objections for cutting the road. In some areas, the strata is very hard laterite rock, Package III - LOA have approved and designing work ongoing, Package II - Site levelling Malappuram PH Dn EE
22 Jun 2023 Work of WTP tendered, LOA approved and design is in prepearation stage. 2nd brace beam work of the approach bridge is progressing and the support columns rising. The Reinforcement of the RCC footing of OHSR Kalanparambu is progressing and footing concreting is in progress. The land for OHSR Vattapparambu is not started yet because the handing over of land to KWA is still in procedure at Panchayath. DI pipes have not arrived. As the rain started, the public raises objections to cutting the road. The land for Vattapparamb had peg marked by Panchayath. Malappuram Sn AE 1
19 Jun 2023 Work of WTP tendered, LOA to be approved from higher office 1st brace beam work of the approach bridge has been completed and the support columns rising. The Reinforcement of the RCC footing of OHSR Kalanparambu is progressing and footing concreting is in progress. . The land for OHSR Vattapparambu is not started yet because the handing over of land to KWA is still in procedure at Panchayath. Laying work is almost completed in the Peringottupulam ward, but DI pipes have not arrived. As the rain started, the public raises objections for cutting the road and the panchayath body also passes a resolution not to allow cutting unless otherwise execute an agreement by KWA with Secretary regarding the restoration. Malappuram Sn AE 1
23 May 2023 1- Package1 - 3% (HDPE pipe supply in progress. The laying work started at Peringottupulam. Supply order to DI Pipes has been gven, but not arrived.) 2- package 2 - 7% completed (Work of approach bridge -footing completed. Earth work completed for OHSR at Kalamparambu. column work in progress) 3 - Package 3- (Work tendered.) Malappuram PH Dn EE
19 May 2023 1- Package1 - 3% (HDPE pipe supply in progress. The laying work started at Peringottupulam. Supply order to DI Pipes has been gven, but not arrived.) 2- package 2 - 7% completed (Work of approach bridge -footing completed. Earth work completed for OHSR at Kalamparambu. column work in progress) 3 - Package 3- (Work tendered.) Malappuram PH Dn EE
16 May 2023 1- Package1 - 3% (HDPE pipe supply in progress. The laying work started at Peringottupulam. Supply order to DI Pipes has been gven, but not arrived.) 2- package 2 - 7% completed (Work of approach bridge -footing completed. Earth work completed for OHSR at Kalamparambu) 3 - Package 3- (Work tendered.) Malappuram PH Dn EE
09 May 2023 1- Package1 - 3% (HDPE pipe supply in progress. The laying work started at Peringottupulam. Supply order to DI Pipes has been gven, but not arrived.) 2- package 2 - 7% completed (Work of approach bridge started. ) 3 - Package 3- (Work tendered.) Malappuram PH Dn EE