Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Jal Jeevan Mission Phase II-2021-22 - Providing Functional House hold tap connection to Kodur Panchayath in Malappuram District

Project Jal Jeevan Mission Phase II-2021-22 - Providing Functional House hold tap connection to Kodur Panchayath in Malappuram District
Project Code MLPJJM09219072
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description 8.00 m Dia well, 8.00 mld WTP, 2 Nos of service reservoirs as Package I and 400 mm DI R W Pumping main, 200 mm CW PM, pump sets, transformers and distribution system in two zones ( HL zone and LL zone) as Package II
Status On-going
District Malappuram
Executing Office Malappuram PH Dn
AS Amount (Rs) 644525000
AS Number G.O.(Rt)No.489/2021/WRD
TS Amount (Rs) 617800000
TS Number Reg .No. 18225/2021-2022
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 68500
Capacity in MLD 8.00
Actual Project Completion Date 31 Mar 2023
Coverage Entire area of Kodur Panchayath
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Jal Jeevan Mission Phase II - Package III- Construction of 8.00 Mld Water treamtment plant Malappuram Sn 1
2 Jal Jeevan Mission Phase II - Package I - Pump sets, Tansformers, RWPM, CWPM and distribution system Malappuram Sn 1
3 Jeevan Mission PhasJale II - Package II - Construction of 6 m dia well ,intake channel , aproach road ,7 LL OHSR Vattamparambu , 16 LL OHSR KALAMPAABA , Interconection work and Compound wall in Kodur pt in Malappuram Dt -Part I A Malappuram Sn 1

Overall Project Status

Status Date Overall Project Status Project Officer Contact
23 Apr 2024 1. Concreting of Filter house wall and beam 1st lift completed. Structural work of sump, clarifier, chlorine room are completed, erection of clarifier bridge in progress. 2. 942m of 400mm DI pumping main at west Kodur, 312.50 m of 250mm DI distribution line at Mundakode, 1040.50m of 200mm DI pumping main and 90mm rider at Mundakode, 1226m of 200mm DI Distribution line along with 1226m of 90mm rider at Vataparambu, 18236m of 90mm, 2450m of 110mm, 723m of 140mm, 2836m of 160mm and 728m of 180mm HDPE pipes laying in progress. Pipe laying work in progress. More pipes arriving. 350 HTC geotagged and going on. No ISA functioning in panchayath. Pipe testing almost completed. The Panchayath members and public raising objections to dig road for pipe line. 3. Side wall concreting 2nd lift completed for 16 LL tank at Kalanparamba. Pump house work nearing completion. The Panchayath authorities not peg marked location for & LL OHSR and hence, the work not started. Malappuram Sn AE 1
06 Nov 2023 WTP:- Concreting of central shaft of clarifier completed. Earthwork of filter bed started. Sklelton work of sump completed Distribution network:- DI pipes not yet arrived. The pump sets will arrive within 2 months. HTC started. The ward members not co-operate for pipe laying work .No ISA functioning in panchayath. Pipe laying in ward No.1 started. The masonry work nearing completion for the pump house. The plastering work progressing. The concreting of columns above third brace beam completed in 16 LL Tank. Work not started to 7 LL tank since the process of handing over the sufficient land by Panchayath not yet completed . Letter submitted to panchayath for speed up this process Malappuram Sn AE 1
26 Sep 2023 In WTP work, The centering work for 2nd lift of the sump wall above the haunch is completed. DI pipe for the scour and inlet of the clarifier is arrived. The centering work of the beams of Chlorinator room started. In distribution works, Hard laterite strata met in the trenches of pipelines in various places. DI pipes are to be arrived. The pump sets will arrive within 2 months.PWD AE insisted to give a new application for road-cutting permission in the ROW portal as per the recent circular by PWD. In Package 2, The lintel and sunshade are completed. The columns of OHSR reached up to 7.00 m. Since the process of handing over sufficient land (Required additional land of 100 sqm) for the 7.00 LL OHSR has not been started. Malappuram Sn AE 1
26 Sep 2023 In WTP work, The centering work for 2nd lift of the sump wall above the haunch is completed. DI pipe for scur &n inlet of the clarifier is arrived. Beam of Chlorinator room started. In distribution works, Hard laterite strata met in the trenches of pipelines in various places. DI pipes are to be arrived. The pump sets will arrive within 2 months. In Package 2, The lintel and sunshade are completed. The columns of OHSR reached up to 7.00 m. Since the process of handing over sufficient land (Required additional land of 100 sqm) for the 7.00 LL OHSR has not been started. Malappuram Sn AE 1
16 Sep 2023 In WTP work, The 1st lift of the sump wall above the haunch is completed. DI pipe for scur &n inlet of the clarifier have to be arrived. In distribution works, Hard laterite strata met in the trenches of pipelines in various places. DI pipes to be arrived. The pump sets will arrive within 2 months. In Package 2, The masonry works for the pump house reached up to the lintel level. The columns of OHSR reached up to 7.00 m. Malappuram Sn AE 1

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 04/11/2022
Scheduled date of Completion of the Project 03 Apr 2024
Expected date of Completion 03/04/2024

Processing Dates

AS Date 18 Sep 2021
TS Date 18 Jan 2022

Other details

Project Officers View