Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
02 Jan 2021 | Pipe laid for a length of 3200m. | Chittur Project Dn - AE 4 | |
16 Dec 2020 | first time extension granted up to 21.02.2021 from 22.09.2020 wide proceedings KWA/PHC/PKD/KIIFB II end tranch/kozinjampara/17-18 dated-15-10-2020 | Chittur Project Dn - AE 4 | |
16 Dec 2020 | first time extention granted up to 31.03.2021 from 22.09.2020 wide order no KWA/PHC/PKD/KIIFB II end tranch/kozinjampara/17-18 dated-15-10-2020 | Chittur Project Dn - AE 4 | |
14 Dec 2020 | 32% of work complete ,250mm DI K9 pipe-2200 m, laid | Chittur Project Dn - AE 4 | |
24 Nov 2020 | 24% OF WORK COMPLETE-Pipe laying work is in progress 250 mm DI K9-1650 M laid out of 6750 m | Chittur Project Dn - AE 4 | |
18 Nov 2020 | Pipe laying in progress . Laid 1550m out of 6750m | Chittur Project Dn - AE 4 | |
13 Nov 2020 | pipe supply completed 250 mm DI K9 pipe-950m laid/ out of 6750 m | Chittur Project Dn - AE 4 | |
12 Oct 2020 | contractor has supplied the pipe at site and laying work start as soon. Testing the pipe at factory only M/c CIPET. | Chittur Project Dn - AE 4 | |
13 Sep 2020 | agreement executed on 1/06/2020, Third party inspection conducted , but test result not obtained ,work delay due to COVID-19. work not started. Date of Completion of this work -22-09-2020. | Chittur Project Dn - AE 4 | |
01 Jul 2020 | agreement executed on 01/06/2020 | Chittur Project Dn - AE 4 |