Status Date Overall Project Status Project Officer Contact
01 Feb 2022 Work in progress | 92% Completed | 01/02/2022 GSB and Wet Mix spreading works in PWD road in progress Chittur Project Dn - AE 4
24 Jan 2022 Work in progress | 92% Completed | 24/01/2022 GSB and Wet Mix spreading works in PWD road in progress Chittur Project Dn - AE 4
20 Jan 2022 Work in progress | 92% Completed | 20/01/2022 GSB and Wet Mix spreading works in PWD road in progress Chittur Project Dn - AE 4
12 Jan 2022 Work in progress | 92% Completed | 12/01/2022 GSB and Wet Mix spreading works in PWD road in progress Chittur Project Dn - AE 4
10 Jan 2022 Work in progress | 92% Completed | 10/01/2022 GSB and Wet Mix spreading works in PWD road in progress Chittur Project Dn - AE 4
02 Jan 2022 Work in progress | 92% Completed | 02/01/2022 GSB and Wet Mix spreading works in PWD road in progress Chittur Project Dn - AE 4
28 Dec 2021 Work in progress | 92% Completed | 28/12/2021 GSB and Wet Mix spreading works in PWD road in progress Chittur Project Dn - AE 4
22 Dec 2021 Work in progress | 92% Completed | 22/12/2021 GSB and Wet Mix spreading works in PWD road in progress Chittur Project Dn - AE 4
21 Dec 2021 Work in progress | 92% Completed | 21/12/2021 GSB and Wet Mix spreading works in PWD road in progress. Chittur Project Dn - AE 4
19 Dec 2021 Work in progress | 92% Completed | 19/12/2021 GSB and Wet Mix spreading works in PWD road under progress. Road survey works and taking of road levels prior to tarring completed. Chittur Project Dn - AE 4