19 May 2021 CC second and part bill prepared Rs50.00 Lakhs. 91% Completed ,Road restoration work pending Chittur Project Dn - AE 4
11 May 2021 CC second and part bill under preparation.91% Completed ,Road restoration work pending Chittur Project Dn - AE 4
29 Apr 2021 CC second and part bill under preparation.91% Completed ,Road restoration work pending Chittur Project Dn - AE 4
28 Apr 2021 CC second and part bill under preparation.91% Completed ,Road restoration work pending , SECOND TIME EXTENTION UP TO 31.5.2021 Chittur Project Dn - AE 4
20 Apr 2021 Work in progress | 91% Completed | 20/04/2021 91 % of the work complete ,Road restoration work pending , SECOND TIME EXTENTION UP TO 31.5.2021 Chittur Project Dn - AE 4
13 Apr 2021 91 % of the work complete Delay due to the Election ban (perumattachattam) , road restoration work -Bitumen has to be taken from BPCL and last linking works also balance , SECOND TIME EXTENTION UP TO 31.5.2021 Chittur Project Dn - AE 4
07 Apr 2021 91 % of the work complete Delay due to the Election ban (perumattachattam) , road restoration work -Bitumen has to be taken from BPCL and last linking works also balance , SECOND TIME EXTENTION UP TO 31.5.2021 Chittur Project Dn - AE 4
31 Mar 2021 250mm CWGM interlinking work almost completed Chittur Project Dn - AE 4
27 Mar 2021 Pipe line work completed and inter connection and linking, road restoration work, testing works to be done .second time extension up to -31.05.2021 Chittur Project Dn - AE 4
17 Mar 2021 work in progress-90% of work complete 250mm DI K9 pipe -total -6.600 km laid Chittur Project Dn - AE 4