Status Date |
Overall Project Status |
Project Officer |
Contact |
19 May 2021 |
CC second and part bill prepared Rs50.00 Lakhs. 91% Completed ,Road restoration work pending |
Chittur Project Dn - AE 4 |
|
11 May 2021 |
CC second and part bill under preparation.91% Completed ,Road restoration work pending |
Chittur Project Dn - AE 4 |
|
29 Apr 2021 |
CC second and part bill under preparation.91% Completed ,Road restoration work pending |
Chittur Project Dn - AE 4 |
|
28 Apr 2021 |
CC second and part bill under preparation.91% Completed ,Road restoration work pending , SECOND TIME EXTENTION UP TO 31.5.2021 |
Chittur Project Dn - AE 4 |
|
20 Apr 2021 |
Work in progress | 91% Completed | 20/04/2021
91 % of the work complete ,Road restoration work pending , SECOND TIME EXTENTION UP TO 31.5.2021 |
Chittur Project Dn - AE 4 |
|
13 Apr 2021 |
91 % of the work complete Delay due to the Election ban (perumattachattam) , road restoration work -Bitumen has to be taken from BPCL and last linking works also balance , SECOND TIME EXTENTION UP TO 31.5.2021 |
Chittur Project Dn - AE 4 |
|
07 Apr 2021 |
91 % of the work complete Delay due to the Election ban (perumattachattam) , road restoration work -Bitumen has to be taken from BPCL and last linking works also balance , SECOND TIME EXTENTION UP TO 31.5.2021 |
Chittur Project Dn - AE 4 |
|
31 Mar 2021 |
250mm CWGM interlinking work almost completed |
Chittur Project Dn - AE 4 |
|
27 Mar 2021 |
Pipe line work completed and inter connection and linking, road restoration work, testing works to be done .second time extension up to -31.05.2021 |
Chittur Project Dn - AE 4 |
|
17 Mar 2021 |
work in progress-90% of work complete
250mm DI K9 pipe -total -6.600 km laid |
Chittur Project Dn - AE 4 |
|