KIIFB PROJECT-CARWSS to kozhinjampara and adjoining villages-Replacement of 200 mm AC clear water gravity main from master OHSR at moongilmada to sathram sump with 200 mm DI k9 pipe for 16000 m-replacement of 200 mm AC Clear water gravity main from master OHSR at oonkilmada to kozhinjampara OHSR with 250 mm DI K9 PIPE FOR 6750 M

Project KIIFB PROJECT-CARWSS to kozhinjampara and adjoining villages-Replacement of 200 mm AC clear water gravity main from master OHSR at moongilmada to sathram sump with 200 mm DI k9 pipe for 16000 m-replacement of 200 mm AC Clear water gravity main from master OHSR at oonkilmada to kozhinjampara OHSR with 250 mm DI K9 PIPE FOR 6750 M
Project Code PKDKIIFB0319689
Type Main project
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description KIIFB PROJECT-CARWSS to kozhinjampara and adjoining villages-Replacement of 200 mm AC clear water gravity main from master OHSR at moongilmada to sathram sump with 200 mm DI k9 pipe for 16000 m-replacement of 200 mm AC Clear water gravity main from master OHSR at moonkilmada to kozhinjampara OHSR with 250 mm DI K9 PIPE FOR 6750 M
Status On-going
District Palakkad
Executing Office Chittur Project Dn
AS Amount (Rs) 58729000
AS Number WRD -005-128-PA-01 OF 2018-2019
TS Amount (Rs) 38200000
TS Number 2019-2020/2019/18397
Total Bill Submitted (Rs) 22997628
Total Bill Paid (Rs) 22997628
Population Benefitted 37412
Capacity in MLD 4.00
Actual Project Completion Date 22 Sep 2020
Coverage Kozhinjampara and adjoining villages
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 KIIFB PROJECT-CARWSS to kozhinjampara and adjoining villages-Replacement of 200 mm AC clear water gravity main Project Division Chittur

Overall Project Status

Status Date Overall Project Status Project Officer Contact
01 Aug 2022 Work has been completed | 100% Completed ON 31/05/2022 Chittur Project Dn - AE 4
08 Jul 2022 Work in progress | 94% Completed | 08/07/2022 total laid-38.50km Supplying 1). 90mm pvc -6kg-35144.00m supplied 2). 110mm pvc-6kg-3030.00m 3).140mmpvc -6kg-486.00m 4).200mm DI-313.50M 5).300mm DI-198.00m 6).20mm pvc-20004.00m Laying 1). 90mm pvc-6kg-34881.60 m laid 2) 110mm pvc-6kg- 2745.60m 3).300mm DI-189.10M 4)200 mm DI-223M 5) 140MM 6kg-120m laid total-38.159Km laid-FHTC- 2307 Connection(3 RD bill-600 Nos,4th bill-729-1785 nos billed) Chittur Project Dn - AE 4
31 May 2022 Work has been completed | 100% Completed | 31/05/2022 Road restoration work completed, PIPE LAYING work completed on 31.3.2021. balance Bill under preparation Chittur Project Dn - AE 4
10 May 2022 Work has been completed | 100% Completed | 10/05/2022 Road restoration work completed, PIPE LAYING work completed on 31.3.2021. balance Bill under preparation Chittur Project Dn - AE 4
02 May 2022 Work in progress | 98% Completed | 02/05/2022 Road restoration work in progress Chittur Project Dn - AE 4

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 23/03/2020
Scheduled date of Completion of the Project 22 Sep 2020
Expected date of Completion 30/04/2022

Processing Dates

AS Date 23 Mar 2019
TS Date 18 Feb 2020

Other details

Project Officers View