KIIFB PROJECT-CARWSS to kozhinjampara and adjoining villages-Replacement of 200 mm AC clear water gravity main from master OHSR at moongilmada to sathram sump with 200 mm DI k9 pipe for 16000 m-replacement of 200 mm AC Clear water gravity main from master OHSR at oonkilmada to kozhinjampara OHSR with 250 mm DI K9 PIPE FOR 6750 M
Project |
KIIFB PROJECT-CARWSS to kozhinjampara and adjoining villages-Replacement of 200 mm AC clear water gravity main from master OHSR at moongilmada to sathram sump with 200 mm DI k9 pipe for 16000 m-replacement of 200 mm AC Clear water gravity main from master OHSR at oonkilmada to kozhinjampara OHSR with 250 mm DI K9 PIPE FOR 6750 M |
Project Code |
PKDKIIFB0319689 |
Type |
Main project |
Funding Agency |
KIIFB |
Category |
KIIFB |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
KIIFB PROJECT-CARWSS to kozhinjampara and adjoining villages-Replacement of 200 mm AC clear water gravity main from master OHSR at moongilmada to sathram sump with 200 mm DI k9 pipe for 16000 m-replacement of 200 mm AC Clear water gravity main from master OHSR at moonkilmada to kozhinjampara OHSR with 250 mm DI K9 PIPE FOR 6750 M |
Status |
On-going |
District |
Palakkad |
Executing Office |
Chittur Project Dn |
AS Amount (Rs) |
58729000
|
AS Number |
WRD -005-128-PA-01 OF 2018-2019 |
TS Amount (Rs) |
38200000 |
TS Number |
2019-2020/2019/18397 |
Total Bill Submitted (Rs) |
22997628 |
Total Bill Paid (Rs) |
22997628 |
Population Benefitted |
37412 |
Capacity in MLD |
4.00 |
Actual Project Completion Date |
22 Sep 2020 |
Coverage |
Kozhinjampara and adjoining villages |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
KIIFB PROJECT-CARWSS to kozhinjampara and adjoining villages-Replacement of 200 mm AC clear water gravity main |
Project Division Chittur |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
01 Aug 2022 |
Work has been completed | 100% Completed ON 31/05/2022 |
Chittur Project Dn - AE 4 |
|
08 Jul 2022 |
Work in progress | 94% Completed | 08/07/2022
total laid-38.50km Supplying 1). 90mm pvc -6kg-35144.00m supplied 2). 110mm pvc-6kg-3030.00m 3).140mmpvc -6kg-486.00m 4).200mm DI-313.50M 5).300mm DI-198.00m 6).20mm pvc-20004.00m Laying 1). 90mm pvc-6kg-34881.60 m laid 2) 110mm pvc-6kg- 2745.60m 3).300mm DI-189.10M 4)200 mm DI-223M 5) 140MM 6kg-120m laid total-38.159Km laid-FHTC- 2307 Connection(3 RD bill-600 Nos,4th bill-729-1785 nos billed) |
Chittur Project Dn - AE 4 |
|
31 May 2022 |
Work has been completed | 100% Completed | 31/05/2022
Road restoration work completed, PIPE LAYING work completed on 31.3.2021. balance Bill under preparation |
Chittur Project Dn - AE 4 |
|
10 May 2022 |
Work has been completed | 100% Completed | 10/05/2022
Road restoration work completed, PIPE LAYING work completed on 31.3.2021. balance Bill under preparation |
Chittur Project Dn - AE 4 |
|
02 May 2022 |
Work in progress | 98% Completed | 02/05/2022
Road restoration work in progress |
Chittur Project Dn - AE 4 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
23/03/2020 |
Scheduled date of Completion of the Project |
22 Sep 2020 |
Expected date of Completion |
30/04/2022 |
Processing Dates
AS Date |
23 Mar 2019 |
TS Date |
18 Feb 2020 |