Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
09 Mar 2021 work in progress-84 % of work complete 250mm DI K9 pipe -total -6.100 km laid Chittur Project Dn - AE 4
07 Mar 2021 Work in progress | 73% Completed | 07/03/2021 Total -6.00km pipe laid,250mm DI K9 pipe laying work and main road crossing works and vaive fixing work are in progress Chittur Project Dn - AE 4
07 Mar 2021 Work in progress | 73% Completed | 07/03/2021 Total -5.60km pipe laid,250mm DI K9 pipe laying work and main road crossing works and vaive fixing work are in progress Chittur Project Dn - AE 4
28 Feb 2021 250mm DI K9 pipe laying work and main road crossing works and vaive fixing work are in progress Chittur Project Dn - AE 4
24 Feb 2021 250mm DI K9 pipe laying work and main road crossing works and vaive fixing work are in progress Chittur Project Dn - AE 4
18 Feb 2021 250mm DI K9 pipe-5.60km laid and valve chamber work ,pressure test works are in progress Chittur Project Dn - AE 4
16 Feb 2021 250mm DI K9 PIPE-5.50 KM laid and valve chamber work in progress Chittur Project Dn - AE 4
06 Feb 2021 Construction of Valve Chamber work in progress. Chittur Project Dn - AE 4
01 Feb 2021 250mm DI K9 PIPE -5.00km laid Chittur Project Dn - AE 4
26 Jan 2021 69 % of work complete 250 mm DI K9 pipe -4700 m laid Chittur Project Dn - AE 4