Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
09 Mar 2021 | work in progress-84 % of work complete 250mm DI K9 pipe -total -6.100 km laid | Chittur Project Dn - AE 4 | |
07 Mar 2021 | Work in progress | 73% Completed | 07/03/2021 Total -6.00km pipe laid,250mm DI K9 pipe laying work and main road crossing works and vaive fixing work are in progress | Chittur Project Dn - AE 4 | |
07 Mar 2021 | Work in progress | 73% Completed | 07/03/2021 Total -5.60km pipe laid,250mm DI K9 pipe laying work and main road crossing works and vaive fixing work are in progress | Chittur Project Dn - AE 4 | |
28 Feb 2021 | 250mm DI K9 pipe laying work and main road crossing works and vaive fixing work are in progress | Chittur Project Dn - AE 4 | |
24 Feb 2021 | 250mm DI K9 pipe laying work and main road crossing works and vaive fixing work are in progress | Chittur Project Dn - AE 4 | |
18 Feb 2021 | 250mm DI K9 pipe-5.60km laid and valve chamber work ,pressure test works are in progress | Chittur Project Dn - AE 4 | |
16 Feb 2021 | 250mm DI K9 PIPE-5.50 KM laid and valve chamber work in progress | Chittur Project Dn - AE 4 | |
06 Feb 2021 | Construction of Valve Chamber work in progress. | Chittur Project Dn - AE 4 | |
01 Feb 2021 | 250mm DI K9 PIPE -5.00km laid | Chittur Project Dn - AE 4 | |
26 Jan 2021 | 69 % of work complete 250 mm DI K9 pipe -4700 m laid | Chittur Project Dn - AE 4 |