| 21 Dec 2023 | Pipeline work has paused since land needs to be acquired for road widening at different sites to continue further works. | Kattappana AEE 1 | |
| 20 Dec 2023 | Pipeline work has paused since land needs to be acquired for road widening at different sites to continue further works. | Kattappana AEE 1 | |
| 19 Dec 2023 | So far laid 3046.5 meters of 90mm PVC pipe, 234 meters of 160 mm PVC pipe, 469.5 meters of 250mm DI and 856 meters of 200mm PVC pipe. | Kattappana AEE 1 | |
| 19 Dec 2023 | Pipeline work has paused since land needs to be acquired for road widening at different sites to continue further works. | Kattappana AEE 1 | |
| 18 Dec 2023 | No work at site due to rain. | Kattappana AEE 1 | |
| 16 Dec 2023 | Pipeline work has paused since land needs to be acquired for road widening at different sites to continue further works. | Kattappana AEE 1 | |
| 15 Dec 2023 | So far laid 3046.5 meters of 90mm PVC pipe, 234 meters of 160 mm PVC pipe, 469.5 meters of 250mm DI and 772 meters of 200mm PVC pipe. | Kattappana AEE 1 | |
| 14 Dec 2023 | So far laid 3046.5 meters of 90mm PVC pipe, 234 meters of 160 mm PVC pipe, 469.5 meters of 250mm DI and 760 meters of 200mm PVC pipe. | Kattappana AEE 1 | |
| 14 Dec 2023 | Ongoing with trenching in rocky areas. | Kattappana AEE 1 | |
| 13 Dec 2023 | Ongoing with trenching in rocky areas. | Kattappana AEE 1 |