DEPOSIT-KRFB-Hill Highway KRFB- Shifting of KWA utilities- Marykulam-Nariyampara
| Project |
DEPOSIT-KRFB-Hill Highway KRFB- Shifting of KWA utilities- Marykulam-Nariyampara |
| Project Code |
IDKGOK112213313 |
| Type |
Main project |
| Funding Agency |
GOK |
| Category |
Deposit Work |
| Type of scheme |
Water Supply |
| Scheme |
4215-01-800-89 |
| Description |
DEPOSIT-KRFB-Hill Highway KRFB-2017-2018-Improvements to Peerumedu, Devikulam Road KM 19/000 to 40/050 and Thodupuzha - Puliyanmala road KM 85/500 to 92/167 in Idukki dist Marykulam-Nariyampara - Shifting of KWA utilities Pipeline work |
| Status |
On-going |
| District |
Idukki |
| Executing Office |
Kattappana Project Dn |
| AS Amount (Rs) |
50359930
|
| AS Number |
KRFB-PMU/MVPA-IDK/HH-PD/2021 |
| TS Amount (Rs) |
27860000 |
| TS Number |
WRD/KWA-CE(CR)/EST_TS/12798/2022_26_1_1 |
| Total Bill Submitted (Rs) |
12318894 |
| Total Bill Paid (Rs) |
12318894 |
| Population Benefitted |
56780 |
| Capacity in MLD |
7.00 |
| Actual Project Completion Date |
06 May 2023 |
| Coverage |
Marykulam-Nariyampara |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
DEPOSIT-KRFB-Hill Highway KRFB- Shifting of KWA utilities- Marykulam-Nariyampara |
Project Division Kattapana |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 08 Jul 2025 |
So far laid 3570.5 metres of 90mm PVC pipe, 4686 metres of 160 mm PVC pipe, 78.5 metres of 200mm DI, 2955 metres of 200mm PVC pipe, 558 metres of 80mm GI pipe, 619 metres of 250mm DI, 106.15 metres of 200mm MS, 15.55 metres of 250mm MS and 276.04 metres of 150mm GI pipe. Total laid 12645.54 m out of 12692 m. |
Kattappana AEE 1 |
|
| 05 Jul 2025 |
So far laid 3570.5 metres of 90mm PVC pipe, 4686 metres of 160 mm PVC pipe, 78.5 metres of 200mm DI, 2955 metres of 200mm PVC pipe, 558 metres of 80mm GI pipe, 619 metres of 250mm DI, 106.15 metres of 200mm MS, 15.55 metres of 250mm MS and 276.04 metres of 150mm GI pipe. Total laid 12645.54 m out of 12692 m. |
Kattapana AE 1 |
|
| 02 Jul 2025 |
So far laid 3570.5 metres of 90mm PVC pipe, 4686 metres of 160 mm PVC pipe, 78.5 metres of 200mm DI, 2955 metres of 200mm PVC pipe, 558 metres of 80mm GI pipe, 619 metres of 250mm DI, 106.15 metres of 200mm MS, 15.55 metres of 250mm MS and 276.04 metres of 150mm GI pipe. Total laid 12645.54 m out of 12692 m. |
Kattapana AE 1 |
|
| 29 Jun 2025 |
So far laid 3570.5 metres of 90mm PVC pipe, 4686 metres of 160 mm PVC pipe, 78.5 metres of 200mm DI, 2955 metres of 200mm PVC pipe, 558 metres of 80mm GI pipe, 619 metres of 250mm DI, 106.15 metres of 200mm MS, 15.55 metres of 250mm MS and 276.04 metres of 150mm GI pipe. Total laid 12645.54 m out of 12692 m. |
Kattappana AEE 1 |
|
| 26 Jun 2025 |
So far laid 3570.5 metres of 90mm PVC pipe, 4686 metres of 160 mm PVC pipe, 78.5 metres of 200mm DI, 2955 metres of 200mm PVC pipe, 558 metres of 80mm GI pipe, 619 metres of 250mm DI, 106.15 metres of 200mm MS, 15.55 metres of 250mm MS and 276.04 metres of 150mm GI pipe. Total laid 12645.54 m out of 12692 m. |
Kattappana AEE 1 |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
15/01/2023 |
| Scheduled date of Completion of the Project |
30 Dec 2024 |
| Expected date of Completion |
30/12/2024 |
Processing Dates
| AS Date |
01 Nov 2022 |
| TS Date |
09 Dec 2022 |