DEPOSIT-KRFB-Hill Highway KRFB- Shifting of KWA utilities- Marykulam-Nariyampara

Project DEPOSIT-KRFB-Hill Highway KRFB- Shifting of KWA utilities- Marykulam-Nariyampara
Project Code IDKGOK112213313
Type Main project
Funding Agency GOK
Category Deposit Work
Type of scheme Water Supply
Scheme 4215-01-800-89
Description DEPOSIT-KRFB-Hill Highway KRFB-2017-2018-Improvements to Peerumedu, Devikulam Road KM 19/000 to 40/050 and Thodupuzha - Puliyanmala road KM 85/500 to 92/167 in Idukki dist Marykulam-Nariyampara - Shifting of KWA utilities Pipeline work
Status On-going
District Idukki
Executing Office Kattappana Project Dn
AS Amount (Rs) 50359930
AS Number KRFB-PMU/MVPA-IDK/HH-PD/2021
TS Amount (Rs) 27860000
TS Number WRD/KWA-CE(CR)/EST_TS/12798/2022_26_1_1
Total Bill Submitted (Rs) 12318894
Total Bill Paid (Rs) 12318894
Population Benefitted 56780
Capacity in MLD 7.00
Actual Project Completion Date 06 May 2023
Coverage Marykulam-Nariyampara

Packages

No. Project Name Location View
1 DEPOSIT-KRFB-Hill Highway KRFB- Shifting of KWA utilities- Marykulam-Nariyampara Project Division Kattapana

Overall Project Status

Status Date Overall Project Status Project Officer Contact
08 Jul 2025 So far laid 3570.5 metres of 90mm PVC pipe, 4686 metres of 160 mm PVC pipe, 78.5 metres of 200mm DI, 2955 metres of 200mm PVC pipe, 558 metres of 80mm GI pipe, 619 metres of 250mm DI, 106.15 metres of 200mm MS, 15.55 metres of 250mm MS and 276.04 metres of 150mm GI pipe. Total laid 12645.54 m out of 12692 m. Kattappana AEE 1
05 Jul 2025 So far laid 3570.5 metres of 90mm PVC pipe, 4686 metres of 160 mm PVC pipe, 78.5 metres of 200mm DI, 2955 metres of 200mm PVC pipe, 558 metres of 80mm GI pipe, 619 metres of 250mm DI, 106.15 metres of 200mm MS, 15.55 metres of 250mm MS and 276.04 metres of 150mm GI pipe. Total laid 12645.54 m out of 12692 m. Kattapana AE 1
02 Jul 2025 So far laid 3570.5 metres of 90mm PVC pipe, 4686 metres of 160 mm PVC pipe, 78.5 metres of 200mm DI, 2955 metres of 200mm PVC pipe, 558 metres of 80mm GI pipe, 619 metres of 250mm DI, 106.15 metres of 200mm MS, 15.55 metres of 250mm MS and 276.04 metres of 150mm GI pipe. Total laid 12645.54 m out of 12692 m. Kattapana AE 1
29 Jun 2025 So far laid 3570.5 metres of 90mm PVC pipe, 4686 metres of 160 mm PVC pipe, 78.5 metres of 200mm DI, 2955 metres of 200mm PVC pipe, 558 metres of 80mm GI pipe, 619 metres of 250mm DI, 106.15 metres of 200mm MS, 15.55 metres of 250mm MS and 276.04 metres of 150mm GI pipe. Total laid 12645.54 m out of 12692 m. Kattappana AEE 1
26 Jun 2025 So far laid 3570.5 metres of 90mm PVC pipe, 4686 metres of 160 mm PVC pipe, 78.5 metres of 200mm DI, 2955 metres of 200mm PVC pipe, 558 metres of 80mm GI pipe, 619 metres of 250mm DI, 106.15 metres of 200mm MS, 15.55 metres of 250mm MS and 276.04 metres of 150mm GI pipe. Total laid 12645.54 m out of 12692 m. Kattappana AEE 1

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 15/01/2023
Scheduled date of Completion of the Project 30 Dec 2024
Expected date of Completion 30/12/2024

Processing Dates

AS Date 01 Nov 2022
TS Date 09 Dec 2022

Other details

Project Officers View