| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 28 Oct 2023 | No work at site due to adverse site conditions. | Kattappana AEE 1 | |
| 25 Oct 2023 | Public holiday and no work due to rain. | Kattappana AEE 1 | |
| 22 Oct 2023 | Work ongoing, DI & PVC laying at site from Nariyampara to Marykulam | Kattappana AEE 1 | |
| 19 Oct 2023 | Work ongoing, DI & PVC laying at site from Nariyampara to Marykulam | Kattappana AEE 1 | |
| 19 Oct 2023 | Work is ongoing at the site from Nariyampara to Marykulam. No pipes have been laid due to adverse site conditions, but trenching in hard rock is in progress. | Kattappana AEE 1 | |
| 16 Oct 2023 | Work ongoing, DI & PVC laying at site from Nariyampara to Marykulam | Kattappana AEE 1 | |
| 13 Oct 2023 | Work ongoing, DI & PVC laying at site from Nariyampara to Marykulam | Kattappana AEE 1 | |
| 10 Oct 2023 | Work ongoing, DI & PVC laying at site from Nariyampara to Marykulam | Kattappana AEE 1 | |
| 07 Oct 2023 | Work ongoing, DI & PVC laying at site from Nariyampara to Marykulam | Kattappana AEE 1 | |
| 10 Oct 2023 | Work ongoing, DI & PVC laying at site from Nariyampara to Marykulam | Kattappana AEE 1 |