| 11 Jan 2024 | Pipeline work has paused since land needs to be acquired for road widening at different sites to continue further works. | Kattappana AEE 1 | |
| 10 Jan 2024 | Pipeline work has paused since land needs to be acquired for road widening at different sites to continue further works. | Kattappana AEE 1 | |
| 09 Jan 2024 | Pipeline work has paused since land needs to be acquired for road widening at different sites to continue further works. | Kattappana AEE 1 | |
| 08 Jan 2024 | Pipeline work has paused since land needs to be acquired for road widening at different sites to continue further works. | Kattappana AEE 1 | |
| 06 Jan 2024 | Pipeline work has paused since land needs to be acquired for road widening at different sites to continue further works. | Kattappana AEE 1 | |
| 05 Jan 2024 | Pipeline work has paused since land needs to be acquired for road widening at different sites to continue further works. | Kattappana AEE 1 | |
| 04 Jan 2024 | Pipeline work has paused since land needs to be acquired for road widening at different sites to continue further works. | Kattappana AEE 1 | |
| 03 Jan 2024 | Pipeline work has paused since land needs to be acquired for road widening at different sites to continue further works. | Kattappana AEE 1 | |
| 02 Jan 2024 | So far laid 3148.5 meters of 90mm PVC pipe, 660 meters of 160 mm PVC pipe, 469.5 meters of 250mm DI and 934 meters of 200mm PVC pipe. | Kattappana AEE 1 | |
| 01 Jan 2024 | Pipeline work has paused since land needs to be acquired for road widening at different sites to continue further works. | Kattappana AEE 1 |