| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 30 Dec 2023 | So far laid 3148.5 meters of 90mm PVC pipe, 516 meters of 160 mm PVC pipe, 469.5 meters of 250mm DI and 934 meters of 200mm PVC pipe. | Kattappana AEE 1 | |
| 30 Dec 2023 | Pipeline work has paused since land needs to be acquired for road widening at different sites to continue further works. | Kattappana AEE 1 | |
| 29 Dec 2023 | So far laid 3148.5 meters of 90mm PVC pipe, 312 meters of 160 mm PVC pipe, 469.5 meters of 250mm DI and 934 meters of 200mm PVC pipe. | Kattappana AEE 1 | |
| 28 Dec 2023 | Pipeline work has paused since land needs to be acquired for road widening at different sites to continue further works. | Kattappana AEE 1 | |
| 27 Dec 2023 | So far laid 3046.5 meters of 90mm PVC pipe, 234 meters of 160 mm PVC pipe, 469.5 meters of 250mm DI and 934 meters of 200mm PVC pipe. | Kattappana AEE 1 | |
| 26 Dec 2023 | Pipeline work has paused since land needs to be acquired for road widening at different sites to continue further works. | Kattappana AEE 1 | |
| 25 Dec 2023 | Pipeline work has paused since land needs to be acquired for road widening at different sites to continue further works. | Kattappana AEE 1 | |
| 24 Dec 2023 | Pipeline work has paused since land needs to be acquired for road widening at different sites to continue further works. | Kattappana AEE 1 | |
| 23 Dec 2023 | Pipeline work has paused since land needs to be acquired for road widening at different sites to continue further works. | Kattappana AEE 1 | |
| 22 Dec 2023 | Pipeline work has paused since land needs to be acquired for road widening at different sites to continue further works. | Kattappana AEE 1 |