| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 02 Feb 2024 | Pipeline works are ongoing. | Kattappana AEE 1 | |
| 01 Feb 2024 | Pressure test works are ongoing. | Kattappana AEE 1 | |
| 31 Jan 2024 | Pipeline work has paused since land needs to be acquired for road widening at different sites to continue further works. | Kattappana AEE 1 | |
| 30 Jan 2024 | Pipeline work has paused since land needs to be acquired for road widening at different sites to continue further works. | Kattappana AEE 1 | |
| 29 Jan 2024 | Pipeline work has paused since land needs to be acquired for road widening at different sites to continue further works. | Kattappana AEE 1 | |
| 27 Jan 2024 | So far laid 3148.5 meters of 90mm PVC pipe, 1,146 meters of 160 mm PVC pipe, 469.5 meters of 250mm DI and 1,264 meters of 200mm PVC pipe. | Kattappana AEE 1 | |
| 29 Jan 2024 | Pipeline work has paused since land needs to be acquired for road widening at different sites to continue further works. | Kattappana AEE 1 | |
| 27 Jan 2024 | Pipeline work has paused since land needs to be acquired for road widening at different sites to continue further works. | Kattappana AEE 1 | |
| 25 Jan 2024 | Pipeline work has paused since land needs to be acquired for road widening at different sites to continue further works. | Kattappana AEE 1 | |
| 24 Jan 2024 | Pipeline work has paused since land needs to be acquired for road widening at different sites to continue further works. | Kattappana AEE 1 |