Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
05 Aug 2022 | Connection 674 completed, 45.5 km pipe supplied, 18.7 km pipe laid, College tank pcc of foundation started, Settling tank concreting work on progress. | Mananthavady PH Sn - AE | |
01 Aug 2022 | Connection 580 completed, 45.5 km pipe supplied, 18.7 km pipe laid, 7LL OHSR earthwork for foundation on progress, Settling tank concreting work on progress. | Mananthavady PH Sn - AE | |
22 Jul 2022 | FHTC 530 COMPLETED, 29KM DISTRIBUTION LINE SUPPLIED. | Mananthavady PH Sn - AE | |
05 Jul 2022 | FHTC on progress | Mananthavady PH Sn - AE | |
01 Jul 2022 | RCC upto haunge completed under curing.FHTC on progress | Mananthavady PH Sn - AE | |
27 Jun 2022 | RCC of settling tank started | Sulthan Bathery PH Dn EE | |
25 Jun 2022 | 24km distribution pipe supplied.16.5 km laying of distribution pipe completed.355 nos.FHTC completed.earth work on dismantled GLSR site at thonichal on progress.shuttering and reinforcement work of settling tank site at WTP Mananthavady on progress | Sulthan Bathery PH Dn EE | |
17 Jun 2022 | distribution pipe -9km laying completed | Sulthan Bathery PH Dn EE | |
13 Jun 2022 | Distribution pipe laying 8 km completed | Sulthan Bathery PH Dn EE | |
10 Jun 2022 | Interconnection works of old pumping line with distribution completed | Sulthan Bathery PH Dn EE |