Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
03 Jun 2022 | pipe replacement for 100 m completed road cutting area | Sulthan Bathery PH Dn EE | |
03 Jun 2022 | pipe replacement at second bridge completed | Sulthan Bathery PH Dn EE | |
03 Jun 2022 | inter connection between pumping main and distribution line completed and trail run success as a part of demolishing 2.5 LL GLSR at Gov. College compound | Sulthan Bathery PH Dn EE | |
03 Jun 2022 | laying work on progress at kallody road | Sulthan Bathery PH Dn EE | |
01 Jun 2022 | Pipe line work in progress. OHSR work started | Sulthan Bathery PH Dn EE | |
26 May 2022 | Almost 5.5 Km pipe laying completed, and 300 FHTCs given | Sulthanbathery PH Sub Dn - AEE | |
26 May 2022 | MORE PIPE SUPPLIED | Sulthan Bathery PH Dn EE | |
26 May 2022 | CLEAR WATER CHANNEL ON PROGRESS | Sulthan Bathery PH Dn EE | |
25 May 2022 | Work in progress | Sulthan Bathery PH Dn EE | |
17 May 2022 | pipe laying started at kallody moolithod CT mukk | Sulthan Bathery PH Dn EE |