Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
03 Jul 2024 | House connection and header line works at Peechangode Ambedkar road | Mananthavady PH Sn - AE | |
29 Jun 2024 | House Connection works at Dwaraka and 4th mile area | Mananthavady PH Sn - AE | |
24 Jun 2024 | 63mm pipe laying at peechangode branch road | Mananthavady PH Sn - AE | |
18 Jun 2024 | House connection works at payode area in progress | Mananthavady PH Sn - AE | |
14 Jun 2024 | House connection works at payode area in progress | Mananthavady PH Sn - AE | |
10 Jun 2024 | pipe Interconnection works at 2/4 area in progress | Mananthavady PH Sn - AE | |
04 Jun 2024 | Plastering work at gov college tank completed | Mananthavady PH Sn - AE | |
31 May 2024 | Interconnection works at dwaraga school road and moolithode in progress. | Mananthavady PH Sn - AE | |
27 May 2024 | 160 mm pipe laying at peechangode-kappumchal | Mananthavady PH Sn - AE | |
20 May 2024 | Plastering work at gov college tank in progress. Thonichal ambedkar road Interconnection completed | Mananthavady PH Sn - AE |