Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
05 Apr 2022 | First lot of pipes ordered. Pipes are ready at Factory. Sent request to CIPET for testing today. Agreed for testing on 25.03.2022. Started giving connections from existing network. | Sulthan Bathery PH Dn EE | |
29 Mar 2022 | Connections being provided from existing feasible lines | Sulthan Bathery PH Dn EE | |
23 Mar 2022 | First lot of pipes ordered. Pipes are ready at Factory. Sent request to CIPET for testing today. Agreed for testing on 25.03.2022. Started giving connections from existing network. | Sulthan Bathery PH Dn EE | |
17 Mar 2022 | First lot of pipes ordered. Pipes are ready at Factory. Sent request to CIPET for testing today. | Sulthan Bathery PH Dn EE | |
11 Mar 2022 | Borehole tests at Tank site completed. Inaugural function has been done with Edavaka GP. First lot of pipes ordered. | Sulthan Bathery PH Dn EE | |
03 Mar 2022 | Borehole tests at Tank site completed. Inaugural function has been done with Edavaka GP. | Sulthan Bathery PH Dn EE | |
23 Feb 2022 | Meeting over with contractor. Sites are shown to the contractor. Borehole tests going on. | Sulthan Bathery PH Dn EE | |
18 Feb 2022 | Meeting over with contractor. Sites are shown to the contractor. Site clearance. | Sulthan Bathery PH Dn EE | |
13 Feb 2022 | Work order issued to Sri Abdul Nazer M, Kozhikkode, and Agreement executed. | Sulthan Bathery PH Dn EE | |
11 Feb 2022 | Work order issued | Sulthan Bathery PH Dn EE |