Overall Project Status

Status Date Overall Project Status Project Officer Contact
05 Apr 2022 First lot of pipes ordered. Pipes are ready at Factory. Sent request to CIPET for testing today. Agreed for testing on 25.03.2022. Started giving connections from existing network. Sulthan Bathery PH Dn EE
29 Mar 2022 Connections being provided from existing feasible lines Sulthan Bathery PH Dn EE
23 Mar 2022 First lot of pipes ordered. Pipes are ready at Factory. Sent request to CIPET for testing today. Agreed for testing on 25.03.2022. Started giving connections from existing network. Sulthan Bathery PH Dn EE
17 Mar 2022 First lot of pipes ordered. Pipes are ready at Factory. Sent request to CIPET for testing today. Sulthan Bathery PH Dn EE
11 Mar 2022 Borehole tests at Tank site completed. Inaugural function has been done with Edavaka GP. First lot of pipes ordered. Sulthan Bathery PH Dn EE
03 Mar 2022 Borehole tests at Tank site completed. Inaugural function has been done with Edavaka GP. Sulthan Bathery PH Dn EE
23 Feb 2022 Meeting over with contractor. Sites are shown to the contractor. Borehole tests going on. Sulthan Bathery PH Dn EE
18 Feb 2022 Meeting over with contractor. Sites are shown to the contractor. Site clearance. Sulthan Bathery PH Dn EE
13 Feb 2022 Work order issued to Sri Abdul Nazer M, Kozhikkode, and Agreement executed. Sulthan Bathery PH Dn EE
11 Feb 2022 Work order issued Sulthan Bathery PH Dn EE