Overall Project Status

Status Date Overall Project Status Project Officer Contact
04 Jul 2023 2001 connections given Mananthavady PH Sn - AE
30 Jun 2023 1994 connections given Mananthavady PH Sn - AE
24 Jun 2023 1982 connections given Mananthavady PH Sn - AE
29 May 2023 1669 connections given. Sulthan Bathery PH Dn EE
24 May 2023 Tank base level beam and slab concreting in progress. 1669 connections given. Sulthan Bathery PH Dn EE
19 May 2023 Tank base level beam and slab concreting in progress. 1669 connections give Sulthan Bathery PH Dn EE
26 Jan 2023 Tank base level beam and slab concreting in progress. 1669 connections given. Sulthan Bathery PH Dn EE
24 Dec 2022 3rd slab casting Mananthavady PH Sn - AE
23 Dec 2022 3rd level slab shuttering. Sulthan Bathery PH Dn EE
05 Dec 2022 2nd level Slab concrete completed. Sulthan Bathery PH Dn EE