Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
30 Nov 2022 | OHSR Work-Beam reinforcement on going. | Sulthan Bathery PH Dn EE | |
18 Nov 2022 | OHSR work - FF Slab concreting completed, pump house slab concreting completed. 1217 FHTCs given | Sulthan Bathery PH Dn EE | |
20 Oct 2022 | OHSR work - columns after plinth beam is progressing. Pipelaying is going on. 1044 FHTCs given. | Sulthan Bathery PH Dn EE | |
05 Oct 2022 | Pump house and Pipe laying work is progress. 7LL OH Tank work- Plinth beam concrete completed. | Sulthan Bathery PH Dn EE | |
26 Sep 2022 | Pump house and 7LL OH Tank work in progress, Pipe laying work is progress. | Sulthan Bathery PH Dn EE | |
12 Sep 2022 | pudding progress and JJM connection 902 completed | Sulthan Bathery PH Dn EE | |
05 Sep 2022 | pudding started and Connection 817 completed, 45.5 km pipe supplied, 18.7 km pipe laid | Sulthan Bathery PH Dn EE | |
30 Aug 2022 | pudding started and Connection 762 completed, 45.5 km pipe supplied, 18.7 km pipe laid | Sulthan Bathery PH Dn EE | |
24 Aug 2022 | pudding started and Connection 762 completed, 45.5 km pipe supplied, 18.7 km pipe laid | Sulthan Bathery PH Dn EE | |
20 Aug 2022 | Connection 762 completed, 45.5 km pipe supplied, 18.7 km pipe laid, Settling tank concreting work on progress. | Mananthavady PH Sn - AE |