AMRUT-Augmentation& Modernization of water supply distribution system in Alappuzha Municipality-Phase 1
Project |
AMRUT-Augmentation& Modernization of water supply distribution system in Alappuzha Municipality-Phase 1 |
Project Code |
ALPAMRUT02172387 |
Type |
Main project |
Funding Agency |
AMRUT |
Category |
AMRUT |
Type of scheme |
Water Supply |
Scheme |
AMRUT |
Description |
AMRUT phase 1,construction of 10LL OHSR Pazhavangadi,construction of 21LL OHSR Kommadi, construction of 12LL OHSR Thattampally, Constrction of 28LL Alisery,construction of drinking water kiosk 1 No,supplying and fixing electromagenetic flow meter at 62mldWTP karumadi,construction of 24*7 customer care |
Status |
Completed |
District |
Alappuzha |
Executing Office |
Alappuzha Project Dn |
AS Amount (Rs) |
244650000
|
AS Number |
534 |
TS Amount (Rs) |
244650000 |
TS Number |
TS/CE/CR |
Total Bill Submitted (Rs) |
207800000 |
Total Bill Paid (Rs) |
207800000 |
Population Benefitted |
350000 |
Capacity in MLD |
64.00 |
Actual Project Completion Date |
31 Mar 2023 |
Coverage |
Alappuzha Municipality |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
AMRUT-Augmentation& Modernization of water supply distribution system in Alappuzha Municipality-Phase 1-Construction of 10 LL OHSR and allied works at Pazhavangady |
Alappuzha Project Dn |
|
2 |
AMRUT-Augmentation& Modernization of water supply distribution system in Alappuzha Municipality-Phase 1-Construction of 12LL OHSR and connected works at Thathampally |
Alappuzha Project Dn |
|
3 |
AMRUT-Augmentation& Modernization of water supply distribution system in Alappuzha Municipality-Phase 1-Construction of 21LL OHSR and connected works at Kommady |
Alappuzha Project Dn |
|
4 |
AMRUT-Augmentation& Modernization of water supply distribution system in Alappuzha Municipality-Phase 1-Construction of 24*7 customer care facility |
Alappuzha Project Dn |
|
5 |
AMRUT-Augmentation& Modernization of water supply distribution system in Alappuzha Municipality-Phase 1-Construction of 28LL OHSR and allied works at Alissery |
Alappuzha Project Dn |
|
6 |
AMRUT-Augmentation& Modernization of water supply distribution system in Alappuzha Municipality-Phase 1-Construction of drinking water kiosk 1 nos |
Alappuzha Project Dn |
|
7 |
AMRUT-Augmentation& Modernization of water supply distribution system in Alappuzha Municipality-Phase 1-Supplying fixing ultra sonic flow meter at 62mld WTP Karumadi |
Alappuzha Project Dn |
|
8 |
Digital survey and design of network |
Alappuzha Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
31 Mar 2023 |
Construction Alissery tank completed, its interconnection works also completed and included in the 100 Days Programme of the Hon'ble Chief minister of Kerala |
Alappuzha Project Dn PM |
|
23 Apr 2022 |
Digital survey and design of work - Completed 2.construction of 10LL OHSR and allied works at Pazhavangadi - Completed 3.construction of 12LL OHSR and connected works at Thathampally- COMPLETED4.construction of 21LL OHSR and connected works at Kommady - COMPLETED5.construction of drinking water kiosk - 1 no. to completed 6.Construction of 28LL OHSR at Alisery- Compound wall completed ,civil work for OHSR completed,office buliding plumbing and electrical, Painting processing 7.supply and fixing electromagnetic flow meter at Karumadi- work Completed. 8. construction of 24*7 customer - Dropped. 28LL OHSR Allissery-Interconnection works in progress |
Alappuzha Project Dn PM |
|
20 Apr 2022 |
Construction work of Alissery tank 98% completed. Finishing works is in progress. Interconnection works to be completed. |
Alappuzha Proj AE |
|
04 Apr 2022 |
Digital survey and design of work - Completed 2.construction of 10LL OHSR and allied works at Pazhavangadi - Completed 3.construction of 12LL OHSR and connected works at Thathampally- COMPLETED4.construction of 21LL OHSR and connected works at Kommady - COMPLETED5.construction of drinking water kiosk - 1 no. to completed 6.Construction of 28LL OHSR at Alisery- Compound wall completed ,civil work for OHSR completed,office buliding plumbing and electrical, Painting processing 7.supply and fixing electromagnetic flow meter at Karumadi- work Completed. 8. construction of 24*7 customer - Dropped |
Alappuzha Proj AE |
|
14 Feb 2022 |
Digital survey and design of work - Completed 2.construction of 10LL OHSR and allied works at Pazhavangadi - Completed 3.construction of 12LL OHSR and connected works at Thathampally- COMPLETED4.construction of 21LL OHSR and connected works at Kommady - COMPLETED5.construction of drinking water kiosk - 1 no. to completed 6.Construction of 28LL OHSR at Alisery- Compound wall completed ,civil work for OHSR completed,office buliding plumbing and electrical, Painting processing 7.supply and fixing electromagnetic flow meter at Karumadi- work Completed. 8. construction of 24*7 customer - Dropped |
Alappuzha Project Dn AE 3 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
16/03/2017 |
Scheduled date of Completion of the Project |
31 Jul 2021 |
Expected date of Completion |
31/05/2022 |
Processing Dates
AS Date |
23 Feb 2017 |
TS Date |
20 Jul 2017 |