Project | AMRUT-Augmentation& Modernization of water supply distribution system in Alappuzha Municipality-Phase 1-Construction of drinking water kiosk 1 nos |
---|---|
Project Code | ALPAMRUT02172387P1 |
Type | Package |
Main Project | AMRUT-Augmentation& Modernization of water supply distribution system in Alappuzha Municipality-Phase 1 |
Funding Agency | AMRUT |
Category | AMRUT |
Type of scheme | Water Supply |
Scheme | AMRUT |
Description | constrcution of drinking water kiosk 1 nos |
Status | On-going |
District | Alappuzha |
Executing Office | Alappuzha Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 1200000 |
TS Number | 13974 |
Technical specification | construction of drinking water kiosk 1 nos |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 22/02/2020 |
---|---|
Scheduled date of Completion as per agreement | 28 Feb 2020 |
Expected date of Completion | 28/02/2021 |
TS Date | 09 Dec 2019 |
---|---|
Estimate Approval | 11 Dec 2019 |
NIT Approval | 13 Dec 2019 |
Supplying and Laying | 20 Dec 2019 |
Tender Closing | 21 Dec 2019 |
Technichal Pre-Qualification | 01 Jan 2020 |
Price bid opening | 10 Jan 2020 |
CE Approval | 13 Jan 2020 |
---|---|
Head Office Approval | 23 Jan 2020 |
Final Approval | 28 Jan 2020 |
Workorder Date | 03 Feb 2020 |
NA | 05 Feb 2020 |
Alappuzha Project Dn PM |
Date: 21/12/2021 |
Work has been completed | 100% Completed
WORK COMPLETED.
Alappuzha Project Dn PM |
Date: 20/12/2021 |
Work has been completed | 100% Completed
work completed.