Project | Digital survey and design of network |
---|---|
Project Code | ALPAMRUT02172387P8 |
Type | Package |
Main Project | AMRUT-Augmentation& Modernization of water supply distribution system in Alappuzha Municipality-Phase 1 |
Funding Agency | AMRUT |
Category | AMRUT |
Type of scheme | Water Supply |
Scheme | AMRUT |
Description | surveying of municipal area |
Status | On-going |
District | Alappuzha |
Executing Office | Alappuzha Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 339000000 |
TS Number | TS/CE/CR |
Technical specification | Digital survey and design of network |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 23/05/2018 |
---|---|
Scheduled date of Completion as per agreement | 29 Oct 2021 |
Expected date of Completion | 31/03/2021 |
TS Date | 04 Jan 2018 |
---|---|
Estimate Approval | 07 Feb 2018 |
NIT Approval | 20 Feb 2018 |
Supplying and Laying | 28 Feb 2018 |
Tender Closing | 02 Mar 2018 |
Technichal Pre-Qualification | 08 Mar 2018 |
Price bid opening | 09 Mar 2018 |
CE Approval | 10 Mar 2018 |
---|---|
Head Office Approval | 19 Mar 2018 |
Board Approval | 22 Mar 2018 |
Final Approval | 31 Mar 2018 |
Workorder Date | 10 Apr 2018 |
NA | 30 Apr 2018 |
Alappuzha Project Dn DPM2 |
Date: 13/09/2020 |
Work has been completed | 100% Completed
completed.