AMRUT-Augmentation& Modernization of water supply distribution system in Alappuzha Municipality-Phase 1-Construction of 21LL OHSR and connected works at Kommady

Project AMRUT-Augmentation& Modernization of water supply distribution system in Alappuzha Municipality-Phase 1-Construction of 21LL OHSR and connected works at Kommady
Project Code ALPAMRUT02172387P6
Type Package
Main Project AMRUT-Augmentation& Modernization of water supply distribution system in Alappuzha Municipality-Phase 1
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description AMRUT-Augmentation& Modernization of water supply distribution system in Alappuzha Municipality-Phase 1-Construction of 21LL OHSR and connected works at Kommady
Status On-going
District Alappuzha
Executing Office Alappuzha Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 49947488
TS Number TS/CE/CR
Technical specification AMRUT-Augmentation& Modernization of water supply distribution system in Alappuzha Municipality-Phase 1-Construction of 21LL OHSR and connected works at Kommady
Contractor Abu Mathew (Mob: 9447037780)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 07/06/2018
Scheduled date of Completion as per agreement 31 Mar 2021
Expected date of Completion 31/12/2020

Processing Dates

TS Date 12 Jan 2018
Estimate Approval 22 Feb 2018
NIT Approval 28 Feb 2018
Supplying and Laying 14 Mar 2018
Tender Closing 31 Mar 2018
Technichal Pre-Qualification 11 Apr 2018
Price bid opening 03 Apr 2018

Approval Dates

CE Approval 22 Apr 2021
Head Office Approval 01 May 2018
Final Approval 15 May 2018
Workorder Date 17 May 2018
NA 07 Jun 2018

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Alappuzha Project Dn AE 3
Date: 04/02/2021

Work has been completed | 100% Completed

work completed.

Alappuzha Project Dn AE 3
Date: 29/01/2021

Work in progress | 97% Completed

painting work completed, interconnection work going on.