Project | AMRUT-Augmentation& Modernization of water supply distribution system in Alappuzha Municipality-Phase 1-Construction of 12LL OHSR and connected works at Thathampally |
---|---|
Project Code | ALPAMRUT02172387P7 |
Type | Package |
Main Project | AMRUT-Augmentation& Modernization of water supply distribution system in Alappuzha Municipality-Phase 1 |
Funding Agency | AMRUT |
Category | AMRUT |
Type of scheme | Water Supply |
Scheme | AMRUT |
Description | Construction of 12LL OHSR and connected works at Thathampally |
Status | On-going |
District | Alappuzha |
Executing Office | Alappuzha Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 31056545 |
TS Number | TS/CE/CR |
Technical specification | Construction of 12LL OHSR and connected works at Thathampally |
Contractor | Abu Mathew (Mob: 9447037780) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 14/08/2018 |
---|---|
Scheduled date of Completion as per agreement | 31 Mar 2021 |
Expected date of Completion | 28/02/2021 |
TS Date | 12 Jan 2018 |
---|---|
Estimate Approval | 07 Feb 2018 |
NIT Approval | 22 Feb 2018 |
Supplying and Laying | 08 Mar 2017 |
Tender Closing | 21 Mar 2018 |
Price bid opening | 23 Mar 2018 |
CE Approval | 26 Apr 2018 |
---|---|
Head Office Approval | 09 May 2018 |
Final Approval | 18 Jul 2018 |
Workorder Date | 30 Jul 2018 |
NA | 14 Aug 2018 |
Alappuzha Project Dn AE 3 |
Date: 30/03/2021 |
Work has been completed | 100% Completed
COMPLETED.
Alappuzha Project Dn AE 3 |
Date: 29/03/2021 |
Work in progress | 99% Completed