Project | AMRUT-Augmentation& Modernization of water supply distribution system in Alappuzha Municipality-Phase 1-Construction of 24*7 customer care facility |
---|---|
Project Code | ALPAMRUT02172387P3 |
Type | Package |
Main Project | AMRUT-Augmentation& Modernization of water supply distribution system in Alappuzha Municipality-Phase 1 |
Funding Agency | AMRUT |
Category | AMRUT |
Type of scheme | Water Supply |
Scheme | AMRUT |
Description | construction of 24*7 customer care facility |
Status | On-going |
District | Alappuzha |
Executing Office | Alappuzha Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 225000 |
TS Number | TS/2020-2021/2021/210 |
Technical specification | construction of 24*7 customer care facility |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 04/01/2020 |
---|---|
Scheduled date of Completion as per agreement | 04 Jan 2021 |
Expected date of Completion | 31/07/2021 |
TS Date | 04 Jan 2020 |
---|---|
Estimate Approval | 28 Jan 2021 |
NIT Approval | 28 Jan 2021 |
Tender Closing | 28 Jan 2021 |
Workorder Date | 04 Jan 2020 |
---|---|
NA | 04 Jan 2020 |
Alappuzha Project Dn AE 3 |
Date: 21/12/2021 |
Work has started | 0% Completed
dropped.
Alappuzha Project Dn PM |
Date: 20/12/2021 |
Work has started | 0% Completed
Dropped.