| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 19 Jul 2022 | Balance pipe to be supplied,Motor for VT pumpsets factory test being arranged | Palakkad Proj AE 3 | |
| 18 Jul 2022 | Balance pipe to be supplied,Motor for VT pumpsets factory test being arranged | Palakkad Proj AE 3 | |
| 17 Jul 2022 | Balance pipe to be supplied,Motor for VT pumpsets factory test being arranged | Palakkad Proj AE 3 | |
| 15 Jul 2022 | Balance pipe to be supplied,Motor for VT pumpsets factory test being arranged | Palakkad Proj AE 3 | |
| 14 Jul 2022 | Balance pipe to be supplied,Motor for VT pumpsets factory test being arranged | Palakkad Proj AE 3 | |
| 13 Jul 2022 | Balance pipe to be supplied,Motor for VT pumpsets factory test being arranged | Palakkad Proj AE 3 | |
| 07 Jul 2022 | Balance pipe to be supplied,Motor for VT pumpsets factory test being arranged | Palakkad Proj AE 3 | |
| 06 Jul 2022 | 3239.50 (out of 6635m)of 400mm DI K9 pipe recieved at site. &1085.5m laying completed.Bhavani River crossing through the riverbed is going on. Finishing works of Intake well, Booster, WTP such as compound wall, plastering, painting, approach road in progress. 400KVA transformer-2no reached thesite. CFPS& VTPS to be supplied.over all 90%completed | Palakkad Proj AE 3 | |
| 05 Jul 2022 | 3239.50 (out of 6635m)of 400mm DI K9 pipe recieved at site. &1085.5m laying completed.Bhavani River crossing through the riverbed is going on. Finishing works of Intake well, Booster, WTP such as compound wall, plastering, painting, approach road in progress. 400KVA transformer-2no reached thesite. CFPS& VTPS to be supplied.over all 90%completed | Palakkad Proj AE 3 | |
| 04 Jul 2022 | 3239.50 (out of 6635m)of 400mm DI K9 pipe recieved at site. &1085.5m laying completed.Bhavani River crossing through the riverbed is going on. Finishing works of Intake well, Booster, WTP such as compound wall, plastering, painting, approach road in progress. 400KVA transformer-2no reached thesite. CFPS& VTPS to be supplied.over all 90%completed | Palakkad Proj AE 3 |