Overall Project Status

Status Date Overall Project Status Project Officer Contact
01 Jul 2025 Pipe to be laid:178.623 km, Pipe supplied:104.309 km, Pipe laid 79 km, HTC given 1436, Dt. of completion 03/05/2024, EOT granted up to 18.07.2025. Kanhangad Proj Dn AE - 2
28 Jun 2025 Pipe to be laid:178.623 km, Pipe supplied:104.309 km, Pipe laid 79 km, HTC given 1436, Dt. of completion 03/05/2024, EOT granted up to 18.07.2025. Kanhangad Proj Dn AE - 2
25 Jun 2025 Pipe to be laid:178.623 km, Pipe supplied:104.309 km, Pipe laid 79 km, HTC given 1436, Dt. of completion 03/05/2024, EOT granted up to 18.07.2025. Kanhangad Proj Dn AE - 2
20 Jun 2025 Pipe to be laid:178.623 km, Pipe supplied:104.309 km, Pipe laid 79 km, HTC given 1436, Dt. of completion 03/05/2024, EOT granted up to 18.07.2025. Kanhangad Proj Dn AE - 2
17 Jun 2025 Pipe to be laid:178.623 km, Pipe supplied:104.309 km, Pipe laid 79 km, HTC given 1436, Dt. of completion 03/05/2024, EOT granted up to 18.07.2025. Kanhangad Proj Dn AE - 2
11 Jun 2025 Pipe to be laid:178.623 km, Pipe supplied:104.309 km, Pipe laid 79 km, HTC given 1436, Dt. of completion 03/05/2024, EOT granted up to 18.07.2025. Kanhangad Proj Dn AE - 2
03 Jun 2025 Pipe to be laid:178.623 km, Pipe supplied:104.309 km, Pipe laid 73 km, HTC given 1436, Dt. of completion 03/05/2024, EOT granted up to 18.07.2025. Kanhangad Proj Dn AE - 2
29 May 2025 Pipe to be laid:178.623 km, Pipe supplied:104.309 km, Pipe laid 73 km, HTC given 1436, Dt. of completion 03/05/2024, EOT granted up to 18.07.2025. Kanhangad Proj Dn AE - 2
26 May 2025 Pipe to be laid:178.623 km, Pipe supplied:104.309 km, Pipe laid 73 km, HTC given 1436, Dt. of completion 03/05/2024, EOT granted up to 18.07.2025. Kanhangad Proj Dn AE - 2
21 May 2025 Pipe to be laid:178.623 km, Pipe supplied:104.309 km, Pipe laid 73 km, HTC given 1436, Dt. of completion 03/05/2024, EOT granted up to 18.07.2025 Kanhangad Proj Dn AE - 2