Overall Project Status

Status Date Overall Project Status Project Officer Contact
10 Jul 2024 Total pipe to be laid 108.452 km, Total pipe laid 45 km, HTC given 1100, Dt. of completion 03/05/2024, EOT requested upto 31/10/2024, permission of PWD and District Panchayath road is yet to be obtained. Kanhangad Proj Dn AE - 2
08 Jul 2024 Total pipe to be laid 108.452 km, Total pipe laid 45 km, HTC given 1100, Dt. of completion 03/05/2024, EOT requested upto 31/10/2024, permission of PWD and District Panchayath road is yet to be obtained. Kanhangad Proj Dn AE - 2
05 Jul 2024 Total pipe to be laid 108.452 km, Total pipe laid 45 km, HTC given 1100, Dt. of completion 03/05/2024, EOT requested upto 31/10/2024, permission of PWD and District Panchayath road is yet to be obtained. Kanhangad Proj Dn AE - 2
03 Jul 2024 Total pipe to be laid 108.452 km, Total pipe laid 45 km, HTC given 1100, Dt. of completion 03/05/2024, EOT requested upto 31/10/2024, permission of PWD and District Panchayath road is yet to be obtained. Kanhangad Proj Dn AE - 2
01 Jul 2024 Total pipe to be laid 108.452 km, Total pipe laid 45 km, HTC given 1100, Dt. of completion 03/05/2024, EOT requested upto 31/10/2024, permission of PWD and District Panchayath road is yet to be obtained. Kanhangad Proj Dn AE - 2
28 Jun 2024 Total pipe to be laid 108.452 km, Total pipe laid 45 km, HTC given 1100, Dt. of completion 03/05/2024, EOT requested upto 31/10/2024, permission of PWD and District Panchayath road is yet to be obtained. Kanhangad Proj Dn AE - 2
26 Jun 2024 Total pipe to be laid 108.452 km, Total pipe laid 44 km, HTC given 1100, Dt. of completion 03/05/2024, EOT requested upto 31/10/2024, permission of PWD and District Panchayath road is yet to be obtained. Kanhangad Proj Dn AE - 2
24 Jun 2024 Total pipe to be laid 108.452 km, Total pipe laid 43 km, HTC given 1100, Dt. of completion 03/05/2024, EOT requested upto 31/10/2024, permission of PWD and District Panchayath road is yet to be obtained. Kanhangad Proj Dn AE - 2
21 Jun 2024 Work in progress. 42 km of pipeline laid. Kanhangad Proj Dn AE - 2
19 Jun 2024 Work in progress. 42 km of pipeline laid. Kanhangad Proj Dn AE - 2