Status Date |
Overall Project Status |
Project Officer |
Contact |
10 Jul 2024 |
Total pipe to be laid 108.452 km, Total pipe laid 45 km, HTC given 1100, Dt. of completion 03/05/2024, EOT requested upto 31/10/2024, permission of PWD and District Panchayath road is yet to be obtained. |
Kanhangad Proj Dn AE - 2 |
|
08 Jul 2024 |
Total pipe to be laid 108.452 km, Total pipe laid 45 km, HTC given 1100, Dt. of completion 03/05/2024, EOT requested upto 31/10/2024, permission of PWD and District Panchayath road is yet to be obtained. |
Kanhangad Proj Dn AE - 2 |
|
05 Jul 2024 |
Total pipe to be laid 108.452 km, Total pipe laid 45 km, HTC given 1100, Dt. of completion 03/05/2024, EOT requested upto 31/10/2024, permission of PWD and District Panchayath road is yet to be obtained. |
Kanhangad Proj Dn AE - 2 |
|
03 Jul 2024 |
Total pipe to be laid 108.452 km, Total pipe laid 45 km, HTC given 1100, Dt. of completion 03/05/2024, EOT requested upto 31/10/2024, permission of PWD and District Panchayath road is yet to be obtained. |
Kanhangad Proj Dn AE - 2 |
|
01 Jul 2024 |
Total pipe to be laid 108.452 km, Total pipe laid 45 km, HTC given 1100, Dt. of completion 03/05/2024, EOT requested upto 31/10/2024, permission of PWD and District Panchayath road is yet to be obtained. |
Kanhangad Proj Dn AE - 2 |
|
28 Jun 2024 |
Total pipe to be laid 108.452 km, Total pipe laid 45 km, HTC given 1100, Dt. of completion 03/05/2024, EOT requested upto 31/10/2024, permission of PWD and District Panchayath road is yet to be obtained. |
Kanhangad Proj Dn AE - 2 |
|
26 Jun 2024 |
Total pipe to be laid 108.452 km, Total pipe laid 44 km, HTC given 1100, Dt. of completion 03/05/2024, EOT requested upto 31/10/2024, permission of PWD and District Panchayath road is yet to be obtained. |
Kanhangad Proj Dn AE - 2 |
|
24 Jun 2024 |
Total pipe to be laid 108.452 km, Total pipe laid 43 km, HTC given 1100, Dt. of completion 03/05/2024, EOT requested upto 31/10/2024, permission of PWD and District Panchayath road is yet to be obtained. |
Kanhangad Proj Dn AE - 2 |
|
21 Jun 2024 |
Work in progress. 42 km of pipeline laid. |
Kanhangad Proj Dn AE - 2 |
|
19 Jun 2024 |
Work in progress. 42 km of pipeline laid. |
Kanhangad Proj Dn AE - 2 |
|