Overall Project Status

Status Date Overall Project Status Project Officer Contact
21 May 2025 Pipe to be laid:178.623 km, Pipe supplied:104.309 km, Pipe laid 73m km, HTC given 1436, Dt. of completion 03/05/2024, EOT granted up to 18.07.2025 Kanhangad Proj Dn AE - 2
17 May 2025 Pipe to be laid:107.552 km, Pipe supplied:104.309 km, Pipe laid 73km, HTC given 1436, Dt. of completion 03/05/2024, EOT granted up to 18.07.2025 Kanhangad Proj Dn AE - 2
17 May 2025 Pipe to be laid:107.552 km, Pipe supplied:104.309 km, Pipe laid 73 km, HTC given 1436, Dt. of completion 03/05/2024, EOT requested to 31.07.2025. Kanhangad Proj Dn AE - 2
14 May 2025 Pipe to be laid:107.552 km, Pipe supplied:104.309 km, Pipe laid 67 km, HTC given 1436, Dt. of completion 03/05/2024, EOT requested to 31.07.2025. Kanhangad Proj Dn AE - 2
08 May 2025 Pipe to be laid:107.552 km, Pipe supplied:104.309 km, Pipe laid 67 km, HTC given 1436, Dt. of completion 03/05/2024, EOT requested to 31.07.2025. Kanhangad Proj Dn AE - 2
05 May 2025 Pipe to be laid:107.552 km, Pipe supplied:104.309 km, Pipe laid 67 km, HTC given 1436, Dt. of completion 03/05/2024, EOT requested to 31.07.2025. Kanhangad Proj Dn AE - 2
30 Apr 2025 Pipe to be laid:107.552 km, Pipe supplied:104.309 km, Pipe laid 67 km, HTC given 1436, Dt. of completion 03/05/2024, EOT requested to 31.07.2025. Kanhangad Proj Dn AE - 2
25 Apr 2025 Pipe to be laid:107.552 km, Pipe supplied:104.309 km, Pipe laid 67 km, HTC given 1436, Dt. of completion 03/05/2024, EOT requested to 31.07.2025. Kanhangad Proj Dn AE - 2
22 Apr 2025 Pipe to be laid:107.552 km, Pipe supplied:104.309 km, Pipe laid 65 km, HTC given 1436, Dt. of completion 03/05/2024, EOT requested to 31.07.2025. Kanhangad Proj Dn AE - 2
16 Apr 2025 Pipe to be laid:107.552 km, Pipe supplied:104.309 km, Pipe laid 60 km, HTC given 1436, Dt. of completion 03/05/2024, EOT requested to 31.07.2025. Kanhangad Proj Dn AE - 2