Status Date |
Overall Project Status |
Project Officer |
Contact |
27 Sep 2024 |
Total pipe to be laid 108.452 km, Total pipe laid 47km, HTC given 1200, Dt. of completion 03/05/2024, EOT granted upto 31/10/2024, permission of PWD and District Panchayath road is yet to be obtained |
Kanhangad Proj Dn AE - 2 |
|
25 Sep 2024 |
Total pipe to be laid 108.452 km, Total pipe laid 47km, HTC given 1200, Dt. of completion 03/05/2024, EOT granted upto 31/10/2024, permission of PWD and District Panchayath road is yet to be obtained |
Kanhangad Proj Dn AE - 2 |
|
23 Sep 2024 |
Total pipe to be laid 108.452 km, Total pipe laid 47km, HTC given 1200, Dt. of completion 03/05/2024, EOT requested upto 31/10/2024, permission of PWD and District Panchayath road is yet to be obtained |
Kanhangad Proj Dn AE - 2 |
|
20 Sep 2024 |
Total pipe to be laid 108.452 km, Total pipe laid 47km, HTC given 1200, Dt. of completion 03/05/2024, EOT requested upto 31/10/2024, permission of PWD and District Panchayath road is yet to be obtained |
Kanhangad Proj Dn AE - 2 |
|
18 Sep 2024 |
Total pipe to be laid 108.452 km, Total pipe laid 47km, HTC given 1200, Dt. of completion 03/05/2024, EOT requested upto 31/10/2024, permission of PWD and District Panchayath road is yet to be obtained. |
Kanhangad Proj Dn AE - 2 |
|
13 Sep 2024 |
Total pipe to be laid 108.452 km, Total pipe laid 47km, HTC given 1200, Dt. of completion 03/05/2024, EOT requested upto 31/10/2024, permission of PWD and District Panchayath road is yet to be obtained. |
Kanhangad Proj Dn AE - 2 |
|
11 Sep 2024 |
Total pipe to be laid 108.452 km, Total pipe laid 47km, HTC given 1200, Dt. of completion 03/05/2024, EOT requested upto 31/10/2024, permission of PWD and District Panchayath road is yet to be obtained. |
Kanhangad Proj Dn AE - 2 |
|
09 Sep 2024 |
Total pipe to be laid 108.452 km, Total pipe laid 47km, HTC given 1200, Dt. of completion 03/05/2024, EOT requested upto 31/10/2024, permission of PWD and District Panchayath road is yet to be obtained. |
Kanhangad Proj Dn AE - 2 |
|
06 Sep 2024 |
Total pipe to be laid 108.452 km, Total pipe laid 47km, HTC given 1200, Dt. of completion 03/05/2024, EOT requested upto 31/10/2024, permission of PWD and District Panchayath road is yet to be obtained. |
Kanhangad Proj Dn AE - 2 |
|
04 Sep 2024 |
Total pipe to be laid 108.452 km, Total pipe laid 47km, HTC given 1200, Dt. of completion 03/05/2024, EOT requested upto 31/10/2024, permission of PWD and District Panchayath road is yet to be obtained. |
Kanhangad Proj Dn AE - 2 |
|