27 Sep 2024 Total pipe to be laid 108.452 km, Total pipe laid 47km, HTC given 1200, Dt. of completion 03/05/2024, EOT granted upto 31/10/2024, permission of PWD and District Panchayath road is yet to be obtained Kanhangad Proj Dn AE - 2
25 Sep 2024 Total pipe to be laid 108.452 km, Total pipe laid 47km, HTC given 1200, Dt. of completion 03/05/2024, EOT granted upto 31/10/2024, permission of PWD and District Panchayath road is yet to be obtained Kanhangad Proj Dn AE - 2
23 Sep 2024 Total pipe to be laid 108.452 km, Total pipe laid 47km, HTC given 1200, Dt. of completion 03/05/2024, EOT requested upto 31/10/2024, permission of PWD and District Panchayath road is yet to be obtained Kanhangad Proj Dn AE - 2
20 Sep 2024 Total pipe to be laid 108.452 km, Total pipe laid 47km, HTC given 1200, Dt. of completion 03/05/2024, EOT requested upto 31/10/2024, permission of PWD and District Panchayath road is yet to be obtained Kanhangad Proj Dn AE - 2
18 Sep 2024 Total pipe to be laid 108.452 km, Total pipe laid 47km, HTC given 1200, Dt. of completion 03/05/2024, EOT requested upto 31/10/2024, permission of PWD and District Panchayath road is yet to be obtained. Kanhangad Proj Dn AE - 2
13 Sep 2024 Total pipe to be laid 108.452 km, Total pipe laid 47km, HTC given 1200, Dt. of completion 03/05/2024, EOT requested upto 31/10/2024, permission of PWD and District Panchayath road is yet to be obtained. Kanhangad Proj Dn AE - 2
11 Sep 2024 Total pipe to be laid 108.452 km, Total pipe laid 47km, HTC given 1200, Dt. of completion 03/05/2024, EOT requested upto 31/10/2024, permission of PWD and District Panchayath road is yet to be obtained. Kanhangad Proj Dn AE - 2
09 Sep 2024 Total pipe to be laid 108.452 km, Total pipe laid 47km, HTC given 1200, Dt. of completion 03/05/2024, EOT requested upto 31/10/2024, permission of PWD and District Panchayath road is yet to be obtained. Kanhangad Proj Dn AE - 2
06 Sep 2024 Total pipe to be laid 108.452 km, Total pipe laid 47km, HTC given 1200, Dt. of completion 03/05/2024, EOT requested upto 31/10/2024, permission of PWD and District Panchayath road is yet to be obtained. Kanhangad Proj Dn AE - 2
04 Sep 2024 Total pipe to be laid 108.452 km, Total pipe laid 47km, HTC given 1200, Dt. of completion 03/05/2024, EOT requested upto 31/10/2024, permission of PWD and District Panchayath road is yet to be obtained. Kanhangad Proj Dn AE - 2