Status Date |
Overall Project Status |
Project Officer |
Contact |
07 Jan 2025 |
Total pipe laid 55 km, HTC given 1436, Dt. of completion 03/05/2024, EOT granted upto 03.03.2025.permission of PWD and District Panchayath road is yet to be obtained. |
Kanhangad Proj Dn AE - 2 |
|
31 Dec 2024 |
Total pipe laid 55 km, HTC given 1436, Dt. of completion 03/05/2024, EOT granted upto 03.03.2025.permission of PWD and District Panchayath road is yet to be obtained. |
Kanhangad Proj Dn AE - 2 |
|
26 Dec 2024 |
Total pipe laid 55 km, HTC given 1436, Dt. of completion 03/05/2024, EOT granted upto 03.03.2025.permission of PWD and District Panchayath road is yet to be obtained. |
Kanhangad Proj Dn AE - 2 |
|
10 Dec 2024 |
Total pipe laid 55 km, HTC given 1436, Dt. of completion 03/05/2024, EOT granted upto 31/10/2024,EOT requested upto 31.03.2025. permission of PWD and District Panchayath road is yet to be obtained. |
Kanhangad Proj Dn AE - 2 |
|
03 Dec 2024 |
Total pipe to be laid 108.452 km, Total pipe laid 49.296km, HTC given 1400, Dt. of completion 03/05/2024, EOT granted upto 31/10/2024,EOT requested upto 31.03.2025. permission of PWD and District Panchayath road is yet to be obtained. |
Kanhangad Proj Dn AE - 2 |
|
30 Nov 2024 |
Total pipe to be laid 108.452 km, Total pipe laid 49.296km, HTC given 1400, Dt. of completion 03/05/2024, EOT granted upto 31/10/2024,EOT requested upto 31.03.2025. permission of PWD and District Panchayath road is yet to be obtained. |
Kanhangad Proj Dn AE - 2 |
|
28 Nov 2024 |
Total pipe to be laid 108.452 km, Total pipe laid 49.296km, HTC given 1300, Dt. of completion 03/05/2024, EOT granted upto 31/10/2024, permission of PWD and District Panchayath road is yet to be obtained. |
Kanhangad Proj Dn AE - 2 |
|
19 Nov 2024 |
Total pipe to be laid 108.452 km, Total pipe laid 49.296km, HTC given 1300, Dt. of completion 03/05/2024, EOT granted upto 31/10/2024, permission of PWD and District Panchayath road is yet to be obtained. |
Kanhangad Proj Dn AE - 2 |
|
13 Nov 2024 |
Total pipe to be laid 108.452 km, Total pipe laid 49.296km, HTC given 1300, Dt. of completion 03/05/2024, EOT granted upto 31/10/2024, permission of PWD and District Panchayath road is yet to be obtained. |
Kanhangad Proj Dn AE - 2 |
|
07 Nov 2024 |
Total pipe to be laid 108.452 km, Total pipe laid 49.296km, HTC given 1300, Dt. of completion 03/05/2024, EOT granted upto 31/10/2024, permission of PWD and District Panchayath road is yet to be obtained. |
Kanhangad Proj Dn AE - 2 |
|